Difference between revisions of "Template:ShortTermSchedule-RGD"
Jump to navigation
Jump to search
Line 52: | Line 52: | ||
:‡ Depending on the stability of detectors in the last higher beam currents run, we can take a 25 M run @ 50 nA. | :‡ Depending on the stability of detectors in the last higher beam currents run, we can take a 25 M run @ 50 nA. | ||
:• Once done, ask for 30 nA (''check with RC/AC after Lumi. scan is done'') and take 100 M electron triggers runs with '''CxC''' target until the end of the Owl shift, but change the DAQ/trigger configuration to: | :• Once done, ask for 30 nA (''check with RC/AC after Lumi. scan is done'') and take 100 M electron triggers runs with '''CxC''' target until the end of the Owl shift, but change the DAQ/trigger configuration to: | ||
− | ::- ''DAQ Config.'': <tt> | + | ::- ''DAQ Config.'': <tt>PROD66_noRICH</tt>. <font color=blue> Follow the DAQ instructions below to change its configurations</font>. |
::- ''Trigger file'': '''rgd_v1.0_no_DC.trg'''. <font color=blue><center>-----''If everything goes well, that should bring us to the Day shift''-----</font></center> | ::- ''Trigger file'': '''rgd_v1.0_no_DC.trg'''. <font color=blue><center>-----''If everything goes well, that should bring us to the Day shift''-----</font></center> | ||
* '''Saturday, Oct. 7th, Day Shift''': | * '''Saturday, Oct. 7th, Day Shift''': | ||
− | :• Continue '''CxC''' data-taking with 30 nA (''TBD after Lumi. scan'') and 100 M triggers runs until the end of the Day shift with the same <tt> | + | :• Continue '''CxC''' data-taking with 30 nA (''TBD after Lumi. scan'') and 100 M triggers runs until the end of the Day shift with the same <tt>PROD66_noRICH</tt> DAQ configuration and '''rgd_v1.0_no_DC.trg''' trigger file.<font color=blue><center>---''If everything goes well, that should bring us to the Swing shift''---</font></center> |
* '''Saturday, Oct. 7th, Swing Shift''': | * '''Saturday, Oct. 7th, Swing Shift''': | ||
:• '''Solid-target, CuSn Configuration, Luminosity Scan''': | :• '''Solid-target, CuSn Configuration, Luminosity Scan''': | ||
Line 69: | Line 69: | ||
::‡ Depending on the stability of detectors in the last higher beam currents run, we can take a 25 M run @ 150 nA. | ::‡ Depending on the stability of detectors in the last higher beam currents run, we can take a 25 M run @ 150 nA. | ||
:• Once done, ask for 125 nA, keep the ''beam blocker in front of the Faraday cup'' (''check with RC/AC after Lumi. scan is done''), and take 100 M electron triggers runs of '''CuSn''' until the end of the Day shift with the following configuration: | :• Once done, ask for 125 nA, keep the ''beam blocker in front of the Faraday cup'' (''check with RC/AC after Lumi. scan is done''), and take 100 M electron triggers runs of '''CuSn''' until the end of the Day shift with the following configuration: | ||
− | ::- ''DAQ Config.'': <tt> | + | ::- ''DAQ Config.'': <tt>PROD66_noRICH</tt>. <font color=blue> Follow the DAQ instructions below to change its configurations</font>. |
::- ''Trigger file'': '''rgd_v1.0_no_DC.trg'''.<font color=blue><center>---''If everything goes well, that should bring us to the Owl shift''---</font></center> | ::- ''Trigger file'': '''rgd_v1.0_no_DC.trg'''.<font color=blue><center>---''If everything goes well, that should bring us to the Owl shift''---</font></center> | ||
* '''Sunday, Oct. 8th, Owl Shift''': | * '''Sunday, Oct. 8th, Owl Shift''': | ||
Line 79: | Line 79: | ||
::- ''Trigger file'': '''rgd_v1.0_no_DC.trg'''. | ::- ''Trigger file'': '''rgd_v1.0_no_DC.trg'''. | ||
:• Once done, we will switch to production mode with outbending configuration: | :• Once done, we will switch to production mode with outbending configuration: | ||
− | ::- ''DAQ Config.'': <tt> | + | ::- ''DAQ Config.'': <tt>PROD66_noRICH</tt>. <font color=blue> Follow the DAQ instructions below to change its configurations and load new trigger files.</font> |
::- ''Trigger file'': '''rgd_out_v1.0.trg'''. | ::- ''Trigger file'': '''rgd_out_v1.0.trg'''. | ||
:• ''To-be-continued''.... | :• ''To-be-continued''.... |
Revision as of 17:58, 6 October 2023
Run Coordinator: Susan Schadmand (757) 575-7540
PDL: Nathan Baltzell (9-)757 876-1789 , x5902 office
RG/Analysis Coordinator (AC): Lamiaa El Fassi (630) 605-4259
Daily RC Meetings at 13:00 in CH Room 200C, and on ZOOM: URL Link (Meeting ID: 1611984219; Passcode: RGD-RC23), except on Wednesdays, which is on ZOOM ONLY @ 15:30 due to the conflict with the 13:30 MCC meeting.
Important Notes
- In case of medical or fire emergency, call 9-911 from a LANDLINE phone in the Counting House
- If you have symptoms or a positive COVID test, do NOT come to your shift - instead, inform the PDL and the RC and JLab medical services immediately to arrange replacements.
- Remote shift: If needed, worker shifts can be taken from off-site. Inform the PDL and RC. Also, make sure that you follow the instructions under the "Worker Shift" Tab - you need some lead time to set up!
- Note to shift takers, please:
- ◊ Read the logbook, be aware of previous 24 hours
- ◊ Arrive at least 10 minutes early for shift change
- ◊ Refresh the run wiki pages; look over them every shift
- - Follow the expert/worker shift instructions
- ◊ Communicate with your co-shift person
- - The shift expert should know about and refer to logbook entries in their shift summary
- - The shift worker should discuss an issue with the shift expert before making extra logbook entries
Run Plan for Oct. 6th to Oct. 8th, 2023
P.S.: Both Engineering-on-call and Xiangdong Wei must be notified ahead of time (at least one hour) to inform them about performing access to change the target position to the solid-target position as well as emptying the target in parallel!
. DAQ configuration
Reference ValuesFSD Thresholds from RG-D
Harp Scan References from RG-D |
General Instructions:
Every Shift:
Every Run:
To access the Hall:
|