Difference between revisions of "Template:ShortTermSchedule-RGK"
Jump to navigation
Jump to search
Line 49: | Line 49: | ||
:: 16:00 – 21:00 – Trigger validation (<font color="red">Valery Kubarovsky</font>) (use PROD67_PIN configuration) | :: 16:00 – 21:00 – Trigger validation (<font color="red">Valery Kubarovsky</font>) (use PROD67_PIN configuration) | ||
::: - Complete trigger validation test plans with DAQ ([https://wiki.jlab.org/clas12-run/images/a/a6/RGK_trigger.pdf RG_K trigger details]) | ::: - Complete trigger validation test plans with DAQ ([https://wiki.jlab.org/clas12-run/images/a/a6/RGK_trigger.pdf RG_K trigger details]) | ||
− | :: 21:00 – 24:00 – Luminosity scans (shifters) (use PROD67 configuration) | + | :: 21:00 – 24:00 – Luminosity scans (shifters) (use PROD67 configuration) (200 MeV ECAL threshold, no DC roads) |
::: - Take runs with 10M events at 10, 20, 30, 40, 50, 60, 75 nA | ::: - Take runs with 10M events at 10, 20, 30, 40, 50, 60, 75 nA | ||
::: - Take 10M event run at 90 nA if possible with DAQ operation (check with RC) | ::: - Take 10M event run at 90 nA if possible with DAQ operation (check with RC) | ||
Line 55: | Line 55: | ||
*'''Saturday, Dec. 16''': | *'''Saturday, Dec. 16''': | ||
− | :: 00:00 – 08:00 – Luminosity scans cont'd (shifters) (use PROD67 configuration) | + | :: 00:00 – 08:00 – Luminosity scans cont'd (shifters) (use PROD67 configuration) (200 MeV ECAL threshold, no DC roads) |
::: - Take runs with 10M events at 10, 20, 30, 40, 50, 60, 75 nA | ::: - Take runs with 10M events at 10, 20, 30, 40, 50, 60, 75 nA | ||
::: - Take 10M event run at 90 nA if possible with DAQ operation(check with RC) | ::: - Take 10M event run at 90 nA if possible with DAQ operation(check with RC) | ||
Line 62: | Line 62: | ||
::: - DC HV studies (75M trigger runs) ([https://wiki.jlab.org/clas12-run/images/e/e7/DCplansRGK.pdf DC test plan document]) | ::: - DC HV studies (75M trigger runs) ([https://wiki.jlab.org/clas12-run/images/e/e7/DCplansRGK.pdf DC test plan document]) | ||
::: - Collect data for gain calibration CTOF, ECAL, FTOF, HTCC | ::: - Collect data for gain calibration CTOF, ECAL, FTOF, HTCC | ||
− | :: 22:00 – 24:00 – Data collection (shifters) (use PROD67 configuration) | + | :: 22:00 – 24:00 – Data collection (shifters) (use PROD67 configuration) (200 MeV ECAL threshold, no DC roads) |
− | |||
::: - Use nominal DC setting defined by Florian | ::: - Use nominal DC setting defined by Florian | ||
*'''Sunday, Dec. 17''': | *'''Sunday, Dec. 17''': | ||
− | :: 00:00 – 08:00 – Data collection (shifters) (use PROD67 configuration) | + | :: 00:00 – 08:00 – Data collection (shifters) (use PROD67 configuration) (200 MeV ECAL threshold, no DC roads) |
::: - Continued data taking from previous shift | ::: - Continued data taking from previous shift | ||
:: 08:00 – 11:00 – Streaming readout tests (<font color="red">Sergey Boyarinov</font>, <font color="red">David Lawrence</font>) | :: 08:00 – 11:00 – Streaming readout tests (<font color="red">Sergey Boyarinov</font>, <font color="red">David Lawrence</font>) | ||
Line 78: | Line 77: | ||
*'''Monday, Dec. 18''': | *'''Monday, Dec. 18''': | ||
− | :: 00:00 – 08:00 – Data collection cont’d (shifters) (use PROD67 configuration) | + | :: 00:00 – 08:00 – Data collection cont’d (shifters) (use PROD67 configuration) (200 MeV ECAL threshold, no DC roads) |
− | |||
::: - Use nominal DC setting defined by Florian | ::: - Use nominal DC setting defined by Florian | ||
:: 08:00 – 14:00 – Reverse solenoid polarity (<font color="red">Eugene Pasyuk</font>, <font color="red">Engineering</font>) | :: 08:00 – 14:00 – Reverse solenoid polarity (<font color="red">Eugene Pasyuk</font>, <font color="red">Engineering</font>) | ||
:: 14:00 – 17:00 – Trigger validation (<font color="red">Valery Kubarovsky</font>) (use PROD67_PIN configuration) | :: 14:00 – 17:00 – Trigger validation (<font color="red">Valery Kubarovsky</font>) (use PROD67_PIN configuration) | ||
::: - Complete trigger validation test plans with DAQ ([https://wiki.jlab.org/clas12-run/images/a/a6/RGK_trigger.pdf RG_K trigger details]) | ::: - Complete trigger validation test plans with DAQ ([https://wiki.jlab.org/clas12-run/images/a/a6/RGK_trigger.pdf RG_K trigger details]) | ||
− | :: 17:00 – 24:00 – Data collection (shifters) (use PROD67 configuration) | + | :: 17:00 – 24:00 – Data collection (shifters) (use PROD67 configuration) (200 MeV ECAL threshold, no DC roads) |
− | |||
::: - Use nominal DC setting defined by Florian | ::: - Use nominal DC setting defined by Florian | ||
*'''Tuesday, Dec. 19''': | *'''Tuesday, Dec. 19''': | ||
− | :: 00:00 – 07:00 – Data collection cont’d (shifters) (use PROD67 configuration) | + | :: 00:00 – 07:00 – Data collection cont’d (shifters) (use PROD67 configuration) (200 MeV ECAL threshold, no DC roads) |
− | |||
::: - Use nominal DC setting defined by Florian | ::: - Use nominal DC setting defined by Florian | ||
:: 07:00 – Beam off | :: 07:00 – Beam off |
Revision as of 14:52, 15 December 2023
Experiment Coordinator: Annalisa D'Angelo
Run Coordinator: Bill Briscoe (757) 575-7540
PDL: Daniel Carman (757) 876-1789; Office: x5586
Daily RC/OA Meetings at 13:00 in CH Room 200C, and on ZOOM: URL Link
Important Notes
Do NOT change FSD settings without approval from RC or beamline expert!
- In case of medical or fire emergency, call 9-911 from a LANDLINE phone in the Counting House and inform the Crew Chief and RC.
- In case of evacuation of the Counting Room (e.g., due to a fire alarm), grab the shift expert phone and leave the room through the "EXIT" door leading to the parking lot. Do not leave through the hallway! Call the RC once outside so the latter will call MCC to turn the beam OFF to Hall B and inform other Hall B staff members.
- If you have symptoms or a positive COVID test, do NOT come to your shift - instead, inform the PDL and the RC and JLab medical services immediately to arrange replacements.
- Remote shift: If needed, worker shifts can be taken from off-site. Inform the PDL and RC. Also, make sure that you follow the instructions under the "Shift Worker" tab, as you need some lead time to set up!
- Note to Shift Takers:
- ◊ Read the ESAD, COO, RSAD, and ERG documents found on the "Current RG-K Run Info" as well as the yellow folder in the counting room. Before you start your first shift on the current experiment, you must sign on the list in the yellow folder. Thereby, you confirm that you have read and understand their content.
- ◊ Read at least the previous 24 hours logbook entries to be aware of recent run details and changes;
- ◊ Arrive at least 10 minutes early for shift change;
- ◊ Refresh the runwiki page/tabs; look over it/them every shift:
- - Follow the Shift Expert/Worker tab's instructions.
- ◊ Do not spend more than 15-20 min trying to fix a problem. In case of any issue, contact the On-call Experts or the RC.
- ◊ Review these important links:
- - Recent Changes and Current Issues
- - General How-to for beam restoration procedures and Møller runs.
Run Plan, Friday, Dec. 15 - Tuesday, Dec. 19, 2023
|
General Instructions
|
DAQ Operation & Related General Instructions
|
|
Reference Values
FSD Thresholds from RG-K
- Upstream: 2 kHz
- Midstream: 2 kHz
- Downstream: 100 kHz
- BOM: 50 kHz
- 5 ms dwell time
Harp Scan References from RG-K
- 2H01 [3]; x= -1.4 mm; y= 0.0 mm
- Tagger (2C24A) [4]: x= -2.0 mm; y= +0.6 mm
- 2C21A [5]: x= -0.4 mm; y= +0.6 mm (less important; values form RG-C)