Daily RC Meetings at 13:00 in CH Room 200C, and on ZOOM: URL Link (Meeting ID: 1605705819), except on Wednesdays, which is @ 15:00 in CH Room 200C and at the same ZOOM link.
Line 34: | Line 34: | ||
:• Configuration: <tt>PROD67</tt> (w/o. PIN option) | :• Configuration: <tt>PROD67</tt> (w/o. PIN option) | ||
:• Trigger: <tt>rge_inb_v1.0_200MeV.trg</tt> | :• Trigger: <tt>rge_inb_v1.0_200MeV.trg</tt> | ||
− | :• Take one | + | :• Take one Empty+Al run @ 70 nA w/. BB for 3 hours (w/. Beam ON)</font> |
* <font color=BLUE>Long-term run plan can be found in this link: [https://docs.google.com/spreadsheets/d/13CvaWromHWRBfxoPrRsy8AD4omTOl0SQkHT6A3mJbRw/edit#gid=967597323], and is outlined below: | * <font color=BLUE>Long-term run plan can be found in this link: [https://docs.google.com/spreadsheets/d/13CvaWromHWRBfxoPrRsy8AD4omTOl0SQkHT6A3mJbRw/edit#gid=967597323], and is outlined below: | ||
− | |||
:# Take one Empty+Empty run @ 200 nA w/. BB for 5 hours (''Call Rafo 20 min in advance to prepare for the BB calibration while the Empty+Al run is close to end''); | :# Take one Empty+Empty run @ 200 nA w/. BB for 5 hours (''Call Rafo 20 min in advance to prepare for the BB calibration while the Empty+Al run is close to end''); | ||
:# Reverse the torus magnet polarity and fill the LD2 target; | :# Reverse the torus magnet polarity and fill the LD2 target; | ||
Line 97: | Line 96: | ||
:• Take one 20 nA run for 3 hours w/. beam ON | :• Take one 20 nA run for 3 hours w/. beam ON | ||
:• Take one 40 nA run for 3 hours w/. beam ON | :• Take one 40 nA run for 3 hours w/. beam ON | ||
+ | :• Take one 55 nA run for 3 hours w/. beam ON | ||
== ''Streaming Readout Test'' == | == ''Streaming Readout Test'' == | ||
Line 159: | Line 159: | ||
* Beamline | * Beamline | ||
− | :• Do not run over 30 minutes above 90 nA with a 5-pass beam without the beam blocker IN. | + | :• Do not run over 30 minutes above 90 nA ('''''50 nA for now while studying FCup behavior''''') with a 5-pass beam without the beam blocker IN. |
:• If there is any concern about beam stability, ask MCC if orbit locks are on (they should be). | :• If there is any concern about beam stability, ask MCC if orbit locks are on (they should be). | ||
:• Document any beam condition change and send scaler GUIs to HBLOG. | :• Document any beam condition change and send scaler GUIs to HBLOG. |
Revision as of 16:38, 16 May 2024
Run Coordinator: Sebouh Paul
Current RP Coordinator: Lamiaa El Fassi (757) 575-7540
PDL: Nathan Baltzell (757) 876-1789, Office: x5902
Important Notes
- In case of medical or fire emergency, call 911 or 9-911 from a LANDLINE phone in the Counting House and inform the Crew Chief and RC.
- In case of evacuation of the Counting Room (e.g., due to a fire alarm), grab the shift expert phone and leave the room through the "EXIT" door leading to the parking lot. Do not leave through the hallway! Call the RC once outside so the latter can call MCC to turn the beam OFF for Hall B and inform other Hall B staff members.
- If you have symptoms or a positive COVID test, do NOT come to your shift. Instead, inform the PDL, the RC, and JLab medical services immediately to arrange replacements.
- In case of a problem with the HV Slow Controls, EPICS in general, please call the primary expert on-call, Nathan Baltzell, before reaching out to anyone else.
- Please put all essential information on the main Hall B logbook HBLOG. Some important alarms have been documented on HBRUN. Use the pulldown menu to choose where an error is reported.
Current Run Plan: May 8th to May 19th
Lumi Scan for LD2+Pb on May 16th
Previous Dual-target Configuration Plans- DC firmware test plan (LD2 + Pb)1) Take one run each with 1M events with the trigger files and beam current at 70 nA
2) Take one run with 500k events and beam current at 35nA with trigger file rge_inb_v1.0_200MeV_dcrb17_2.trg 3) Take one run with 500k events and beam current at 35nA with trigger file rge_inb_v1.0_200MeV_dcrb17_4.trg
*** Notes ***
LD2+Pb runs
LD2+Sn runs
LD2+Al runs
Lumi Scan for LD2+Al on May 15th
Lumi Scan for LD2+Pb on May 15th - 16th
Streaming Readout Test
|
References- BPM Positions
- Harp Scans- FSD Thresholds
- Charge Asymmetry- Upstream Halo counters
|
General Reminders
|
DAQ Operation
|