Difference between revisions of "Run Meeting: August 10th, 2020"

From clas12-run
Jump to navigation Jump to search
(Created page with "==Summary of past 24h:== Sunday, August 9 to Monday, August 10 5-pass data taking at 200 nA on deuterium (about 4 M events) Accelerator down time from 12 PM to about midnigh...")
 
 
(One intermediate revision by the same user not shown)
Line 3: Line 3:
 
Sunday, August 9 to Monday, August 10
 
Sunday, August 9 to Monday, August 10
  
5-pass data taking at 200 nA on deuterium (about 4 M events)
+
5-pass data taking at 200 nA on deuterium (about 4 M events).
 +
 
 
Accelerator down time from 12 PM to about midnight.
 
Accelerator down time from 12 PM to about midnight.
Beam halo caused by Hall C high current beam (27 micro A) leads to FSD trips in Hall B
+
 
Take data on deuterium with 60 nA during parts of the night
+
Beam halo caused by Hall C high current beam (27 micro A) leads to FSD trips in Hall B.
Regular 5-pass data taking with 200 nA beam resumed at 8:30  
+
 
Deuterium target purged opportunistically at 11 AM
+
Take data on deuterium with 60 nA during parts of the night.
 +
 
 +
Regular 5-pass data taking with 200 nA beam resumed at 8:30.
 +
 
 +
Deuterium target purged opportunistically at 11 AM.
  
  
Line 14: Line 19:
  
 
Data taking.
 
Data taking.
 +
 
Tuesday morning accelerator down for maintenance and repairs.
 
Tuesday morning accelerator down for maintenance and repairs.
 
Hall B magnets will be turned down during maintenance for MPS COMM repairs.
 
Hall B magnets will be turned down during maintenance for MPS COMM repairs.

Latest revision as of 11:34, 10 August 2020

Summary of past 24h:

Sunday, August 9 to Monday, August 10

5-pass data taking at 200 nA on deuterium (about 4 M events).

Accelerator down time from 12 PM to about midnight.

Beam halo caused by Hall C high current beam (27 micro A) leads to FSD trips in Hall B.

Take data on deuterium with 60 nA during parts of the night.

Regular 5-pass data taking with 200 nA beam resumed at 8:30.

Deuterium target purged opportunistically at 11 AM.


Plan for next 24 hours

Data taking.

Tuesday morning accelerator down for maintenance and repairs. Hall B magnets will be turned down during maintenance for MPS COMM repairs.