Line 31: | Line 31: | ||
* '''All shifts are canceled until Tuesday, Oct. 3rd, Day shift due to the target work delay'''. | * '''All shifts are canceled until Tuesday, Oct. 3rd, Day shift due to the target work delay'''. | ||
* '''Tuesday, Oct. 3rd''': | * '''Tuesday, Oct. 3rd''': | ||
− | :• | + | :• Start with tuning the beam to the tagger dump. Once done, take a 1.5-hour Møller run with a new quadrupole power supply and tagger ramping/degaussing. '''Eugene plans to be present as the beamline expert'''. |
− | :• | + | :• Next, switch to tuning beam to Faraday cup. It may take 2.5 hours to ramp up the solenoid and torus to full current. The solenoid will be gradually ramped up to half field intensity, then full, then the torus will be turned on and ramped up to full inbending current. During this process, keep an eye on the deflection at the viewer. '''Eugene plans to be present as the beamline expert'''. |
:• '''Trigger validation''': | :• '''Trigger validation''': | ||
::‡ The trigger experts, Valery and Rafo, need to be notified before starting this run. Then, call MCC, ask for 35 nA, and take a 4-hour-long (''read the N.B. below'') LD2 target run with a ''30 kHz random trigger'' to validate the electron trigger. ''Please note that a 4-h-long run is needed while the BEAM is ON; thus, adjust the end-of-run accordingly to account for any beam trips and hiccups'': | ::‡ The trigger experts, Valery and Rafo, need to be notified before starting this run. Then, call MCC, ask for 35 nA, and take a 4-hour-long (''read the N.B. below'') LD2 target run with a ''30 kHz random trigger'' to validate the electron trigger. ''Please note that a 4-h-long run is needed while the BEAM is ON; thus, adjust the end-of-run accordingly to account for any beam trips and hiccups'': | ||
Line 46: | Line 46: | ||
:::- ''DAQ Config.'': <tt>PROD66_PIN</tt> | :::- ''DAQ Config.'': <tt>PROD66_PIN</tt> | ||
:::- ''Trigger file'': '''rgd_v1.0_no_DC_35nA.trg'''. <font color=blue> Follow the DAQ instructions below to load a new trigger file</font>. | :::- ''Trigger file'': '''rgd_v1.0_no_DC_35nA.trg'''. <font color=blue> Follow the DAQ instructions below to load a new trigger file</font>. | ||
− | ::‡ Ask MCC for 35 nA beam current and take a few LD2 runs with 4 DC HV settings. A total of 180 M electron triggers is needed for this study: two HV settings with 75 M each and the other two with 15 M each. More information can be found at [https://wiki.jlab.org/clas12-run/images/2/2a/DCplansRGD.pdf]. '''Florian needs to be called to change the DC HV | + | ::‡ Ask MCC for 35 nA beam current and take a few LD2 runs with 4 DC HV settings. A total of 180 M electron triggers is needed for this study: two HV settings with 75 M each and the other two with 15 M each. More information can be found at [https://wiki.jlab.org/clas12-run/images/2/2a/DCplansRGD.pdf]. '''Florian needs to be called to change the DC HV after the first 75 M run with the default current setting (R1/R2/R3: 10/10/10 V)'''. |
::‡ '''P.S.: During the DC HV scan runs, please call (''at least 30 min in advance'') the SVT/MVT experts, Yuri and Rafo, to perform their CVT bias scans'''. | ::‡ '''P.S.: During the DC HV scan runs, please call (''at least 30 min in advance'') the SVT/MVT experts, Yuri and Rafo, to perform their CVT bias scans'''. | ||
::‡ '''Parasitically''', 75 M electron triggers are needed for the TOF gain calibration. | ::‡ '''Parasitically''', 75 M electron triggers are needed for the TOF gain calibration. |
Revision as of 17:20, 3 October 2023
Run Coordinator: Lamiaa El Fassi (757) 575-7540
PDL: Nathan Baltzell (9-)757 876-1789 , x5902 office
RG/Analysis Coordinator (AC): Lamiaa El Fassi (630) 605-4259
Daily RC Meetings at 13:00 in CH Room 200C, and on ZOOM: URL Link (Meeting ID: 1611984219; Passcode: RGD-RC23), except on Wednesdays, which is on ZOOM ONLY @ 15:30 due to the conflict with the 13:30 MCC meeting.
Important Notes
- In case of medical or fire emergency, call 9-911 from a LANDLINE phone in the Counting House
- If you have symptoms or a positive COVID test, do NOT come to your shift - instead, inform the PDL and the RC and JLab medical services immediately to arrange replacements.
- Remote shift: If needed, worker shifts can be taken from off-site. Inform the PDL and RC. Also, make sure that you follow the instructions under the "Worker Shift" Tab - you need some lead time to set up!
- Note to shift takers, please:
- ◊ Read the logbook, be aware of previous 24 hours
- ◊ Arrive at least 10 minutes early for shift change
- ◊ Refresh the run wiki pages; look over them every shift
- - Follow the expert/worker shift instructions
- ◊ Communicate with your co-shift person
- - The shift expert should know about and refer to logbook entries in their shift summary
- - The shift worker should discuss an issue with the shift expert before making extra logbook entries
Run Plan for Oct. 3rd to Oct. 7th, 2023
. DAQ configuration
Reference ValuesFSD Thresholds from RG-C (to-be-changed for RG-D)
Harp Scan References from RG-C (to-be-changed for RG-D) |
General Instructions:
Every Shift:
Every Run:
To access the Hall:
|