Line 91: | Line 91: | ||
::‡ Ask MCC for 90 nA and take a 5 M triggers run with the following trigger file: | ::‡ Ask MCC for 90 nA and take a 5 M triggers run with the following trigger file: | ||
:::- ''Trigger file'': '''rgd_v1.0_no_DC_90nA.trg'''. | :::- ''Trigger file'': '''rgd_v1.0_no_DC_90nA.trg'''. | ||
− | ::‡ We will scan three beam currents in this 5 M triggers run. Ask MCC for 110 nA, take roughly 1.5 M events, ''monitor the DC occupancy in mon12'', then increase the current to 120 nA, take another 1.5 M events, ''refresh mon12 and monitor the DC occupancy'', and then increase the current to 130 nA for the last 2 M events while ''monitoring the DC occupancy in mon12'', but with the following trigger file: | + | ::‡ We will scan three beam currents in this 5 M triggers run. Ask MCC for 110 nA, insert ''beam blocker in front of the Faraday cup'', and take roughly 1.5 M events, ''monitor the DC occupancy in mon12'', then increase the current to 120 nA, take another 1.5 M events, ''refresh mon12 and monitor the DC occupancy'', and then increase the current to 130 nA for the last 2 M events while ''monitoring the DC occupancy in mon12'', but with the following trigger file: |
:::- ''Trigger file'': '''rgd_v1.0_no_DC_100nA.trg'''. <font color=blue> Follow the DAQ instructions below to load a new trigger file</font>. | :::- ''Trigger file'': '''rgd_v1.0_no_DC_100nA.trg'''. <font color=blue> Follow the DAQ instructions below to load a new trigger file</font>. | ||
− | ::‡ ''Once done, take a 25 M run @ 130 nA with the same trigger file and DAQ configuration''. | + | ::‡ ''Once done, take a 25 M run @ 130 nA with the same trigger file and DAQ configuration'' as well as the ''beam blocker. |
::‡ Next, we will scan much higher beam currents in the last 5 M triggers run with this target. Ask MCC for 150 nA, take roughly 1.5 M events, ''monitor the DC occupancy in mon12'', then increase the current to 175 nA for another 1.5 M events, ''refresh mon12 and monitor the DC occupancy'', and then increase the current to 200 nA for the last 2 M events while ''monitoring the DC occupancy in mon12''.. <font color=brown>Depending on the detector's performance (HV trips?) during this run, the beam current can be reduced until the level at which the trips cease. If approaching the current of the previously taken run, check with the RC or AC whether the luminosity scan should stop or whether this last scan should be taken at a specific current value. </font> | ::‡ Next, we will scan much higher beam currents in the last 5 M triggers run with this target. Ask MCC for 150 nA, take roughly 1.5 M events, ''monitor the DC occupancy in mon12'', then increase the current to 175 nA for another 1.5 M events, ''refresh mon12 and monitor the DC occupancy'', and then increase the current to 200 nA for the last 2 M events while ''monitoring the DC occupancy in mon12''.. <font color=brown>Depending on the detector's performance (HV trips?) during this run, the beam current can be reduced until the level at which the trips cease. If approaching the current of the previously taken run, check with the RC or AC whether the luminosity scan should stop or whether this last scan should be taken at a specific current value. </font> | ||
::‡ Depending on the stability of detectors in the last higher beam currents run, we can take a 25 M run @ 150 nA. | ::‡ Depending on the stability of detectors in the last higher beam currents run, we can take a 25 M run @ 150 nA. | ||
− | :• Once done, ask for 125 nA (''check with RC/AC after Lumi. scan is done'') and take 100 M electron triggers runs of '''CuSn''' until the end of the Day shift with the following configuration: | + | :• Once done, ask for 125 nA, keep the ''beam blocker in front of the Faraday cup'' (''check with RC/AC after Lumi. scan is done''), and take 100 M electron triggers runs of '''CuSn''' until the end of the Day shift with the following configuration: |
::- ''DAQ Config.'': <tt>PROD66</tt>. <font color=blue> Follow the DAQ instructions below to change its configurations</font>. | ::- ''DAQ Config.'': <tt>PROD66</tt>. <font color=blue> Follow the DAQ instructions below to change its configurations</font>. | ||
::- ''Trigger file'': '''rgd_v1.0_no_DC.trg'''.<font color=blue><center>---''If everything goes well, that should bring us to the Swing shift''---</font></center> | ::- ''Trigger file'': '''rgd_v1.0_no_DC.trg'''.<font color=blue><center>---''If everything goes well, that should bring us to the Swing shift''---</font></center> |
Revision as of 23:11, 4 October 2023
Run Coordinator: Susan Schadmand (757) 575-7540
PDL: Nathan Baltzell (9-)757 876-1789 , x5902 office
RG/Analysis Coordinator (AC): Lamiaa El Fassi (630) 605-4259
Daily RC Meetings at 13:00 in CH Room 200C, and on ZOOM: URL Link (Meeting ID: 1611984219; Passcode: RGD-RC23), except on Wednesdays, which is on ZOOM ONLY @ 15:30 due to the conflict with the 13:30 MCC meeting.
Important Notes
- In case of medical or fire emergency, call 9-911 from a LANDLINE phone in the Counting House
- If you have symptoms or a positive COVID test, do NOT come to your shift - instead, inform the PDL and the RC and JLab medical services immediately to arrange replacements.
- Remote shift: If needed, worker shifts can be taken from off-site. Inform the PDL and RC. Also, make sure that you follow the instructions under the "Worker Shift" Tab - you need some lead time to set up!
- Note to shift takers, please:
- ◊ Read the logbook, be aware of previous 24 hours
- ◊ Arrive at least 10 minutes early for shift change
- ◊ Refresh the run wiki pages; look over them every shift
- - Follow the expert/worker shift instructions
- ◊ Communicate with your co-shift person
- - The shift expert should know about and refer to logbook entries in their shift summary
- - The shift worker should discuss an issue with the shift expert before making extra logbook entries
Run Plan for Oct. 4th to Oct. 8th, 2023
P.S.: Both Denny and Xiaodong must be notified ahead of time (at least 1/2h) to inform them about performing access to change the target position to the solid-foil position as well as emptying the target in parallel!
. DAQ configuration
Reference ValuesFSD Thresholds from RG-D
Harp Scan References from RG-D |
General Instructions:
Every Shift:
Every Run: