== '''Run Plan''' for Wed, Oct. 18 - Sat., Oct. 21, 2023 == | == '''Run Plan''' for Wed, Oct. 18 - Sat., Oct. 21, 2023 == | ||
* '''Wednesday Day Shift''': | * '''Wednesday Day Shift''': | ||
− | :• '''MCC Beam Studies'''! | + | :• '''MCC Beam Studies and Maintenance'''! |
* '''Wednesday Swing Shift''': | * '''Wednesday Swing Shift''': | ||
:• '''As soon as the MCC is ready to send the beam, please call Eugene'''. Please follow the steps to establish the beam to tagger dump, energize the tagger magnet, and take a harp scan in 2C21 and 2C24 using 5 nA beam current. Please log your results. Then, Eugene will take a Møller run with a 1/2-wave plate out. | :• '''As soon as the MCC is ready to send the beam, please call Eugene'''. Please follow the steps to establish the beam to tagger dump, energize the tagger magnet, and take a harp scan in 2C21 and 2C24 using 5 nA beam current. Please log your results. Then, Eugene will take a Møller run with a 1/2-wave plate out. |
Revision as of 10:30, 18 October 2023
Run Coordinator: Susan Schadmand (757) 575-7540 (or 757-223-6213)
PDL: Nathan Baltzell (9-)757 876-1789 , x5902 office
RG/Analysis Coordinator (AC): Lamiaa El Fassi (630) 605-4259
Daily RC/OA Meetings at 13:00 in CH Room 200C, and on ZOOM: URL Link (Meeting ID: 1611984219; Passcode: RGD-RC23), except on Wednesdays, which is on ZOOM ONLY @ 15:30 due to the conflict with the 13:30 MCC Scheduling/Planning meeting.
Important Notes
Do NOT change FSD settings without approval from RC or beamline expert!
- In case of medical or fire emergency, call 9-911 from a LANDLINE phone in the Counting House
- If you have symptoms or a positive COVID test, do NOT come to your shift - instead, inform the PDL and the RC and JLab medical services immediately to arrange replacements.
- Remote shift: If needed, worker shifts can be taken from off-site. Inform the PDL and RC. Also, make sure that you follow the instructions under the "Worker Shift" Tab - you need some lead time to set up!
- Note to shift takers, please:
- ◊ Read the logbook, be aware of previous 24 hours
- ◊ Arrive at least 10 minutes early for shift change
- ◊ Refresh the run wiki pages; look over them every shift
- - Follow the expert/worker shift instructions
- ◊ Communicate with your co-shift person
- - The shift expert should know about and refer to logbook entries in their shift summary
- - The shift worker should discuss an issue with the shift expert before making extra logbook entries
- ◊ For advice, do not hesitate to call the RC first and foremost, day or night.
Current Issues
- BMT/FMT/SVT:
- ◊ If new hot channels appear, please call the MVT/SVT/MM expert Yuri Gotra (757-541-7539) to address them.
- ◊ SVT low voltage alarms (minor, every ~2 hours) is a communication problem in the system, not an issue with the voltages. Acknowledge the alarm.
- The '"ECAL_adcSum" histograms in mon12 are filled depending on trigger bits 0-6, which are prescaled in the current outbending configuration trigger file "rgd_out_v1.1.trg" by a factor of 20; see HBLOG entry #: 4201027. Thus, the relatively smaller number of histogram entries.
- Tagger magnet procedure If the tagger magnet needs to be turned off, tell the operator to use only the script only for degaussing, NEVER do "by hand"!
- Change the LD2 and solid targets positions in the hall: In case of questions from MCC about the necessary controlled access, please refer to the logbook entry #: 4196113 for the access requirements.
Run Plan for Wed, Oct. 18 - Sat., Oct. 21, 2023
DAQ configuration
Reference ValuesFSD Thresholds from RG-D
Harp Scan References from RG-D
IA for Q Asymmetry |
General Instructions
Every Shift:
Every Run:
To access the Hall:
|