(Created page with "'''Run Coordinator: Lamiaa El Fassi''' (757) 575-7540 ''' PDL: Nathan Baltzell''' (9-)757 876-1789 , x5902 office ''' [https://x Daily RC Meetings] at 15:30: CH Room 200C,...") |
|||
Line 30: | Line 30: | ||
* '''Thursday, Sept. 14th''': The current plan is to lock down the hall in the day shift and start tunning beam to the tagger dump in the swing/owl shift. | * '''Thursday, Sept. 14th''': The current plan is to lock down the hall in the day shift and start tunning beam to the tagger dump in the swing/owl shift. | ||
* '''Friday, Sept. 15th''': | * '''Friday, Sept. 15th''': | ||
− | ** If the beam is successfully tuned overnight to the tagger dump, take a 1.5-hour Moller run with new quadrupole power supply and tagger ramping/degaussing; <font color=red>Does Eugene (or another beamline expert?) need to be | + | ** If the beam is successfully tuned overnight to the tagger dump, take a 1.5-hour Moller run with new quadrupole power supply and tagger ramping/degaussing; <font color=red>Does Eugene (or another beamline expert?) need to be consulted for this? </font> |
− | ** Start tuning beam to Faraday cup. It may take 2.5 hours to ramp up the solenoid and torus to full current. The solenoid will be gradually ramped up to half field intensity, then full, then the torus will be turned on and ramped up to full inbending current. During this process, keep an eye on the deflection on the viewer; <font color=red>Does Eugene (or another expert?) need to be | + | ** Start tuning beam to Faraday cup. It may take 2.5 hours to ramp up the solenoid and torus to full current. The solenoid will be gradually ramped up to half field intensity, then full, then the torus will be turned on and ramped up to full inbending current. During this process, keep an eye on the deflection on the viewer; <font color=red>Does Eugene (or another expert?) need to be called for this? </font> |
+ | ** | ||
* In-bending torus field, 5-pass beam on ND3. | * In-bending torus field, 5-pass beam on ND3. |
Revision as of 13:22, 7 September 2023
Run Coordinator: Lamiaa El Fassi (757) 575-7540
PDL: Nathan Baltzell (9-)757 876-1789 , x5902 office
Daily RC Meetings at 15:30: CH Room 200C, and on Zoom: Link, Meeting ID: 1611984219, Passcode: RGD-RC23
Important Notes
- In case of medical or fire emergency, call 9-911 from a LANDLINE phone in the Counting House
- If you have symptoms or a positive COVID test, do NOT come to your shift - instead, inform the PDL and the RC and JLab medical services immediately to arrange replacements.
- Remote shift: If needed, worker shifts can be taken from off-site. Inform the PDL and RC. Also, make sure that you follow the instructions under the "Worker Shift" Tab - you need some lead time to set up!
Note to shift takers, please:
- Read the logbook, be aware of previous 24 hours
- Arrive at least 10 minutes early for shift change
- Refresh the run wiki pages; look over them every shift
- Follow the expert/worker shift instructions
- Communicate with your co-shift person
- The shift expert should know about and refer to logbook entries in their shift summary
- The shift worker should discuss an issue with the shift expert before making extra logbook entries
LE: Please don't change: Work in progress
Short-Term Schedule for the Week from Sept 13th to Sept. 20th, 2023
DAQ configuration
Reference ValuesFSD Thresholds from RG-C
Harp Scan References from RG-C |
General Instructions:
Every Shift:
Every Run:
To access the Hall:
|