− | == Short-Term Schedule for the Week from '''Sept | + | == Short-Term Schedule for the Week from '''Sept. 22nd to Sept. 25th''', 2023 == |
− | * ''' | + | * '''All shifts are canceled until Friday, Sept. 22nd, due to the target work and/or MCC beam/maintenance studies'''. |
− | * '''Thursday, Sept. | + | * '''Thursday, Sept. 21st''': The tentative plan if everything progresses well with the target work is to lock up the hall in the day shift and start tunning the beam to the tagger dump in the swing/owl shift. |
− | * '''Friday, Sept. | + | * '''Friday, Sept. 22nd''': |
** If the beam is successfully tuned overnight to the tagger dump, take a 1.5-hour Moller run with new quadrupole power supply and tagger ramping/degaussing; <font color=red>Does Eugene (or another beamline expert?) need to be consulted for this? </font> | ** If the beam is successfully tuned overnight to the tagger dump, take a 1.5-hour Moller run with new quadrupole power supply and tagger ramping/degaussing; <font color=red>Does Eugene (or another beamline expert?) need to be consulted for this? </font> | ||
** Start tuning beam to Faraday cup. It may take 2.5 hours to ramp up the solenoid and torus to full current. The solenoid will be gradually ramped up to half field intensity, then full, then the torus will be turned on and ramped up to full inbending current. During this process, keep an eye on the deflection on the viewer; <font color=red>Does Eugene (or another expert?) need to be called for this? </font> | ** Start tuning beam to Faraday cup. It may take 2.5 hours to ramp up the solenoid and torus to full current. The solenoid will be gradually ramped up to half field intensity, then full, then the torus will be turned on and ramped up to full inbending current. During this process, keep an eye on the deflection on the viewer; <font color=red>Does Eugene (or another expert?) need to be called for this? </font> | ||
** '''Trigger validation''': | ** '''Trigger validation''': | ||
− | *** Call MCC and ask for 35 nA and take 4 hours LD2 target run with a ''random trigger'' to validate electron trigger; | + | *** Call MCC and ask for 35 nA and take 4 hours LD2 target run with a ''30 kHz random trigger'' to validate electron trigger; |
− | **** ''Trigger file: | + | **** ''Trigger file'': '''rgd_250MeV_v1.0_30kHz.trg'''. <font color=blue> Follow the DAQ instructions below to load a new trigger file</font>. |
− | *** Take one hour LD2 run with | + | *** Take one hour LD2 run with e- trigger with ''no-DC-roads'' to validate the trigger roads. |
− | **** ''Trigger file: | + | **** ''Trigger file'': '''rgd_250MeV_v1.0_no_DC.trg'''. <font color=blue> Follow the DAQ instructions below to load a new trigger file</font>. |
** '''Parasitic studies''': | ** '''Parasitic studies''': | ||
*** When it's convenient, perform a slow beam current ramps up for scaler linearity. That can be done over the phone with the MCC ops using a 5 nA beam current increase steps until reaching 35 nA while starting the random trigger run. The process should take 5 to 7 min at max. | *** When it's convenient, perform a slow beam current ramps up for scaler linearity. That can be done over the phone with the MCC ops using a 5 nA beam current increase steps until reaching 35 nA while starting the random trigger run. The process should take 5 to 7 min at max. | ||
*** The SVT/MVT expert could perform any SVT/MVT studies that fit within ongoing activities prior to production. (<font color=red>''Comments and suggestions are welcome''</font>) <font color=blue><center>-------- ''If everything goes well, that should bring us to the Swing shift'' -------</font></center> | *** The SVT/MVT expert could perform any SVT/MVT studies that fit within ongoing activities prior to production. (<font color=red>''Comments and suggestions are welcome''</font>) <font color=blue><center>-------- ''If everything goes well, that should bring us to the Swing shift'' -------</font></center> | ||
**'''DC HV Scan, TOF Gain and ECAL Calibrations''': | **'''DC HV Scan, TOF Gain and ECAL Calibrations''': | ||
− | *** ''All runs will be taken with the | + | *** ''All runs will be taken with the e- trigger without DC-roads until the trigger roads are validated by the trigger team.''. |
+ | **** ''Trigger file'': '''rgd_250MeV_v1.0_no_DC.trg'''. <font color=blue> Follow the DAQ instructions below to load a new trigger file</font>. | ||
***Ask MCC for 45 nA beam current and take 5 hours runs with different DC HV settings. A total of 120 M electron triggers is needed for this study. '''Florian needs to be consulted'''. (<font color=red>''I can't access Florian's table in Nathan's shared RG-D Special Runs document. Please, Florian, advise what needs to be specified here!''</font>) | ***Ask MCC for 45 nA beam current and take 5 hours runs with different DC HV settings. A total of 120 M electron triggers is needed for this study. '''Florian needs to be consulted'''. (<font color=red>''I can't access Florian's table in Nathan's shared RG-D Special Runs document. Please, Florian, advise what needs to be specified here!''</font>) | ||
***Take 1.5-hour run with just EPICS, no DAQ. '''Florian needs to be consulted'''. (<font color=red>''I can't access Florian's document due to some expired access error??? </font>) | ***Take 1.5-hour run with just EPICS, no DAQ. '''Florian needs to be consulted'''. (<font color=red>''I can't access Florian's document due to some expired access error??? </font>) | ||
Line 48: | Line 49: | ||
*** Parasitically, the same data can be used to conduct a linearity study for the new ECAL sector 5 PMTs. '''Cole needs to be consulted'''. (<font color=red>'' Please, Cole, advise what needs to be specified here!''</font>) | *** Parasitically, the same data can be used to conduct a linearity study for the new ECAL sector 5 PMTs. '''Cole needs to be consulted'''. (<font color=red>'' Please, Cole, advise what needs to be specified here!''</font>) | ||
** '''Coarse Luminosity Scan''': | ** '''Coarse Luminosity Scan''': | ||
− | *** This first study is needed for TOF/ECAL linearity and AI training. A series of runs will be taken with the following beam currents: | + | *** This first study is needed for TOF/ECAL linearity and AI training. A series of runs will be taken with the following beam currents and the same electron trigger without DC roads: |
+ | **** ''Trigger file'': '''rgd_250MeV_v1.0_no_DC.trg'''. | ||
**** Ask MCC for 5 nA and take a 5 M run with the '''TBD''' inbending e- trigger with no-DC-roads. The random prescale factor needs to be decreased. <font color=red>''Who should be notified about that, and for which beam current it should increase back? </font> <font color=blue><center>-------- ''If everything goes well, that should bring us to the Owl shift'' -------</font></center> | **** Ask MCC for 5 nA and take a 5 M run with the '''TBD''' inbending e- trigger with no-DC-roads. The random prescale factor needs to be decreased. <font color=red>''Who should be notified about that, and for which beam current it should increase back? </font> <font color=blue><center>-------- ''If everything goes well, that should bring us to the Owl shift'' -------</font></center> | ||
− | * '''Saturday, Sept. | + | * '''Saturday, Sept. 23rd''': |
** '''Luminosity Scan''': | ** '''Luminosity Scan''': | ||
− | *** Continue the study for the following beam currents: | + | *** Continue the study for the following beam currents and the same electron trigger without DC roads: |
− | **** Whenever the 5 nA run is done, ask MCC for 10 nA and take a 5 M run | + | **** ''Trigger file'': '''rgd_250MeV_v1.0_no_DC.trg'''. |
− | **** Ask MCC for 25 nA and take a 5 M run | + | **** Whenever the 5 nA run is done, ask MCC for 10 nA and take a 5 M run. |
− | **** Ask MCC for 35 nA and take a 5 M run | + | **** Ask MCC for 25 nA and take a 5 M run. |
− | **** Ask MCC for 50 nA and take a 5 M run | + | **** Ask MCC for 35 nA and take a 5 M run. <font color=blue><center>-------- ''If everything goes well, the Day shift should start somewhere in between these runs!'' -------</font></center> |
+ | **** Ask MCC for 50 nA and take a 5 M run. | ||
**** Once done, we could perform a high-current luminosity scan (''to-be-revised based on the feedback''). If so, ask MCC for: | **** Once done, we could perform a high-current luminosity scan (''to-be-revised based on the feedback''). If so, ask MCC for: | ||
− | ***** 75 nA and take a 50 M run | + | ***** 75 nA and take a 50 M run. |
− | ***** 100 nA and take a 50 M run | + | ***** 100 nA and take a 50 M run. <font color=red>Depending on the detector's performance (HV trips?), the beam current can be reduced to 90 nA or until the level that the trips cease. Would that work? </font> |
** Once done, Valery should be called to change the RICH to a high threshold setting, then take a 100 M electron trigger run with 35 nA (~ 4h run). <font color=red>''Please, Valery, advise whether you want to take this run now with no-DC-roads, assuming all other subsystems will be at their nominal settings!''</font>) | ** Once done, Valery should be called to change the RICH to a high threshold setting, then take a 100 M electron trigger run with 35 nA (~ 4h run). <font color=red>''Please, Valery, advise whether you want to take this run now with no-DC-roads, assuming all other subsystems will be at their nominal settings!''</font>) | ||
** Once done, the RICH setting can be reverted. '''Valery may need to be contacted again'''. Continue LD2 data-taking with 35 nA and 100 M runs until the end of the shift.<font color=blue><center>---''If everything goes well, that should bring us to the Swing shift'' ---</font></center> | ** Once done, the RICH setting can be reverted. '''Valery may need to be contacted again'''. Continue LD2 data-taking with 35 nA and 100 M runs until the end of the shift.<font color=blue><center>---''If everything goes well, that should bring us to the Swing shift'' ---</font></center> | ||
* '''Target Changeover''': | * '''Target Changeover''': | ||
** Denny/the target group (''TBD'') needs to be called ahead of time to ensure that the controlled access to change the target in the hall and boiling off LD2 will be done within 1/2h. | ** Denny/the target group (''TBD'') needs to be called ahead of time to ensure that the controlled access to change the target in the hall and boiling off LD2 will be done within 1/2h. | ||
− | ** Put the flag assembly in the C+C target configuration, then ask MCC for 30 nA and take 1/2h run with the ''' | + | ** Put the flag assembly in the C+C target configuration, then ask MCC for 30 nA and take a 1/2h run with the same electron trigger without DC roads: |
+ | *** ''Trigger file'': '''rgd_250MeV_v1.0_no_DC.trg'''. | ||
** '''Solid-target Luminosity Scans''': | ** '''Solid-target Luminosity Scans''': | ||
*** '''C+C target configuration''': | *** '''C+C target configuration''': | ||
− | **** Ask MCC for 10 nA and take a 5 M run | + | **** Ask MCC for 10 nA and take a 5 M run. |
− | **** Ask MCC for 20 nA and take a 5 M run | + | **** Ask MCC for 20 nA and take a 5 M run. |
− | **** Ask MCC for 30 nA and take a 5 M run | + | **** Ask MCC for 30 nA and take a 5 M run. |
− | **** Ask MCC for 40 nA and take a 5 M run | + | **** Ask MCC for 40 nA and take a 5 M run. |
− | **** Ask MCC for 50 nA and take a 5 M run | + | **** Ask MCC for 50 nA and take a 5 M run. |
*** '''Cu+Sn target configuration''': | *** '''Cu+Sn target configuration''': | ||
− | **** Ask MCC for 90 nA and take a 5 M run | + | **** Ask MCC for 90 nA and take a 5 M run. |
− | **** Ask MCC for 100 nA and take a 5 M run | + | **** Ask MCC for 100 nA and take a 5 M run. |
− | **** Ask MCC for 110 nA and take a 5 M run | + | **** Ask MCC for 110 nA and take a 5 M run. |
− | **** Ask MCC for 120 nA and take a 5 M run | + | **** Ask MCC for 120 nA and take a 5 M run. |
− | **** Ask MCC for 130 nA and take a 5 M run | + | **** Ask MCC for 130 nA and take a 5 M run. |
− | **** Ask MCC for 150 nA and take a 5 M run | + | **** Ask MCC for 150 nA and take a 5 M run. |
− | **Once done, ask for 130 nA and take 100 M runs of Cu+Sn until the end of the shift with the same ''' | + | **Once done, ask for 130 nA and take 100 M runs of Cu+Sn until the end of the shift with the same electron trigger without DC roads: |
+ | *** ''Trigger file'': '''rgd_250MeV_v1.0_no_DC.trg'''. | ||
<!--font color=blue><center>---''If everything goes well, the Owl shift should start somewhere in between the listed Cu+Sn luminosity scan runs!'' ---</font></center--> | <!--font color=blue><center>---''If everything goes well, the Owl shift should start somewhere in between the listed Cu+Sn luminosity scan runs!'' ---</font></center--> | ||
− | * ''' | + | * '''Sept. 24th''': |
<!--** If the Owl shift starts with an ongoing luminosity scan for Cu+Sn, please continue the study to complete the listed beam current runs. --> | <!--** If the Owl shift starts with an ongoing luminosity scan for Cu+Sn, please continue the study to complete the listed beam current runs. --> | ||
** Continue Cu+Sn data-taking with 130 nA and 100 M runs until the end of the Owl shift. | ** Continue Cu+Sn data-taking with 130 nA and 100 M runs until the end of the Owl shift. | ||
** Continue Cu+Sn data-taking with 130 nA and 100 M runs until the end of the day shift. | ** Continue Cu+Sn data-taking with 130 nA and 100 M runs until the end of the day shift. | ||
** By the beginning of the swing shift, change the target configuration to C+C, then ask MCC for 30 nA and take at least 6h of 100 M runs. | ** By the beginning of the swing shift, change the target configuration to C+C, then ask MCC for 30 nA and take at least 6h of 100 M runs. | ||
− | ** ''Plans may change'' but assuming the MCC MD will be on Monday, Sept. | + | ** ''Plans may change'' but assuming the MCC MD will be on Monday, Sept. 25th (''similarly to the week of Sept 11th MD''), we should check with Denny/target group when they can come in to move the target back to LD2 position. The target won't be filled for the alignment run. <font color=red>Eugene may need to be contacted to ramp down the torus and solenoid magnets. </font> |
− | ** Ask for 1 nA, and take 10 M electron triggers run with zero-field. <font color=red> Please, Yuri, advise whether you need to be contacted to set anything for the parasitic CVT alignment </font> | + | ** Ask for 1 nA, and take 10 M electron triggers run with zero-field and the following electron trigger based on CTOFxCND coincidence and without DC roads: |
+ | *** ''Trigger file'': '''rgd_250MeV_v1.0_zero.trg'''. <font color=blue> Follow the DAQ instructions below to load a new trigger file</font>. | ||
+ | <!--font color=red> Please, Yuri, advise whether you need to be contacted to set anything for the parasitic CVT alignment </font--> | ||
* '''Monday, Sept. 18th''': | * '''Monday, Sept. 18th''': | ||
** MCC maintenance/beam studies during the day shift (''TBC'')! | ** MCC maintenance/beam studies during the day shift (''TBC'')! | ||
Line 100: | Line 107: | ||
== <font color=blue> DAQ configuration </font> == | == <font color=blue> DAQ configuration </font> == | ||
− | * Configuration is currently <tt>'''PROD66'''</tt>/<tt>''TBD for RG-D''</tt>, | + | * Configuration is currently <tt>'''PROD66'''</tt>/<tt>''TBD for RG-D''</tt>, <tt>Trigger file: '''rgd_250MeV_v1.0_no_DC.trg''' without DC roads</tt>. |
* '''NOTE''': UNLESS a RICH problem crashes the DAQ, do NOT interrupt an otherwise smooth run to make a RICH recovery - instead, do this in between runs. | * '''NOTE''': UNLESS a RICH problem crashes the DAQ, do NOT interrupt an otherwise smooth run to make a RICH recovery - instead, do this in between runs. | ||
* '''NOTE''': BOTH the shift expert AND the shift worker MUST check and reset monitoring histograms at least once every 30-60 minutes to make sure there are no major detector problems. Sometimes, it is the only way to know that a roc needs to be rebooted. | * '''NOTE''': BOTH the shift expert AND the shift worker MUST check and reset monitoring histograms at least once every 30-60 minutes to make sure there are no major detector problems. Sometimes, it is the only way to know that a roc needs to be rebooted. |
Revision as of 21:34, 11 September 2023
Run Coordinator: Lamiaa El Fassi (757) 575-7540
PDL: Nathan Baltzell (9-)757 876-1789 , x5902 office
Daily RC Meetings at 13:00: CH Room 200C, and on ZOOM, except on Wednesdays, which is in ZOOM ONLY @ 15:30 due to the conflict with the 1:30 PM MCC meeting: Link, Meeting ID: 1611984219, Passcode: RGD-RC23
Important Notes
- In case of medical or fire emergency, call 9-911 from a LANDLINE phone in the Counting House
- If you have symptoms or a positive COVID test, do NOT come to your shift - instead, inform the PDL and the RC and JLab medical services immediately to arrange replacements.
- Remote shift: If needed, worker shifts can be taken from off-site. Inform the PDL and RC. Also, make sure that you follow the instructions under the "Worker Shift" Tab - you need some lead time to set up!
Note to shift takers, please:
- Read the logbook, be aware of previous 24 hours
- Arrive at least 10 minutes early for shift change
- Refresh the run wiki pages; look over them every shift
- Follow the expert/worker shift instructions
- Communicate with your co-shift person
- The shift expert should know about and refer to logbook entries in their shift summary
- The shift worker should discuss an issue with the shift expert before making extra logbook entries
Short-Term Schedule for the Week from Sept. 22nd to Sept. 25th, 2023
DAQ configuration
Reference ValuesFSD Thresholds from RG-C (to-be-changed for RG-D)
Harp Scan References from RG-C (to-be-changed for RG-D) |
General Instructions:
Every Shift:
Every Run:
To access the Hall:
|