Run Meeting: August 21st, 2020
Back to Run Group F | Daily Run Group F Coordination Meetings
12:00PM RC Meeting (https://bluejeans.com/7576835804)
RC: M. Hattawy
Summary of Aug. 21th
Owl shift
- Shift summary by the shift expert: shift was cancelled.
- Issues: NL vacuum issue.
- Recorded data: 0
Day shift
- Shift summary by the shift expert: https://logbooks.jlab.org/entry/3831852
- Issues: NO beam because of the NL vacuum issue.
- Recorded data: zero
Swing shift
- Shift summary by the shift expert: https://logbooks.jlab.org/entry/3831991
- Issues: a power supply was tripped at the end of the HWP out moller run. Eugene said, this will take time to fix/replace the power supply and we decided to move with sending the beam to FC.
- Recorded data: nothing yet ... (21:13 )
Whole day summary
- Total recorded data today:
- Part-II total accumulated data on D2: 754M + ...
- Concerns:
Tomorrow daily RC meeting will be at usual time 12:00 PM using the link https://bluejeans.com/7576835804/