== <font color=blue>''' Run Plan: beamline commissioning'''</font>==
 
== <font color=blue>''' Run Plan: beamline commissioning'''</font>==
 
   
 
   
* Start the beamline commissioning following the instructions described in [https://wiki.jlab.org/clas12-run/images/7/74/CLAS12_beamline_commissioning.pdf]. At the start of this procedure, make sure the following conditions are established: all CLAS12 detectors are off, both solenoid and torus magnets are off and target is empty.
+
* Make sure the following conditions are established: all CLAS12 detectors are off, both solenoid and torus magnets are off and target is empty.
 +
* Start the beamline commissioning following the instructions described in [https://wiki.jlab.org/clas12-run/images/7/74/CLAS12_beamline_commissioning.pdf].  
 
* Record every relevant information in the logbook
 
* Record every relevant information in the logbook
  

Revision as of 17:44, 6 December 2017

[edit]
Role Phone Number
Hall B Run Coordinator (757) 575-7540 (cell)
Hall B Physics Division Liaison (757) 876-1789 (cell)
MCC 7048
Crew Chief 7045
Crew Chief (757) 876-3367 (cell)
Program Deputy (757) 876-7997 (cell)
RadCon (757) 876-1743 (cell)
Gate House Guard 5822
Location Phone Number
Hall B Floor 5165
Hall B Space Frame 5170 and 5171
Hall B Forward Carriage 5371
Hall B Gas Shed 7115
Hall B Counting House 5244 (Shift Expert)
Hall B Counting House (757) 329-4846 (Shift Expert cell)
Hall B Counting House 5245 or 5126 (Shift Worker)
Hall A Counting House 5501
Hall C Counting House 6000
Hall D Counting House 5504
Hall B System Phone Number On-Call Person
Engineering (757) 748-5048 (cell)
(757) 897-9060 (cell)
Engineering On-Call (primary)
Denny Insley (secondary)
Slow Controls (757) 748-6922 (cell) Nathan Baltzell
Beamline (757) 303-3996 (cell) Eugene Pasyuk
DC (757) 218-4372 (cell)
(757) 748-5048 (cell)
Florian Hauenstein (primary)
Engineering On-Call (secondary)
SVT/MVT/MM (757) 541-7539 (cell)
(757) 753-7769 (cell)
Yuri Gotra (primary)
Rafo Paremuzyan (secondary)
ECAL (757) 810-1489 (cell) Cole Smith
FTOF/CTOF (757) 344-7204 (cell) Daniel Carman
CND (757) 329-4844 (cell) Pierre Chatagnon
HTCC/LTCC (757) 344-7174 (cell) Youri Sharabian
FT (757) 344-1848 (cell) Raffaella De Vita
BAND (757) 310-7198 (cell) Florian Hauenstein
RICH (757) 344-3235 (cell)
(757) 748-6922 (cell)
Valery Kubarovsky (primary)
Nathan Baltzell (secondary)
DAQ (757) 232-6221 (cell) Sergey Boiarinov
Cryotarget (757) 218-2266 (cell)
(757) 871-5374 (cell)
(757) 897-1415 (cell)
(757) 746-9277 (cell)
Xiangdong Wei (first)
James Brock (second)
James Maxwell (third)
Chris Keith (fourth)
RG-E Solid Target (757) 344-1848 (cell) Antonio Radic
Authorized Hall B Solenoid/Torus Operators
Hall B Denny Insley, Morgan Cook, Eugene Pasyuk
Magnet Group Probir Ghosha, Renuka Rajput-Ghoshal
Detector Support Group Brian Eng, Pablo Campero, Tyler Lemon
DC Power Onish Kumar, Sarin Philip
  • Note, all non-JLab numbers must be dialed with an area code. When calling from a counting-house landline, dial "9" first.
  • To call JLab phones from outside the lab, all 4-digit numbers must be preceded by 757-269
  • Click Here to edit Phone Numbers. Note, you then also have to edit the current page to force a refresh.

Click Here to edit Phone Numbers. Note, you then also have to edit this page to force a refresh.


CLAS12 Engineering Run, Fall 2017
Beam energy 10.6 GeV (5 pass)
Important: Document all your work in the logbook!

RC: Raffaella DeVita

  • (757) 575-7540
  • 9 575 7540 from Counting Room
  • devita@jlab.org

PDL: Eugene Pasyuk

  • (757) 876-1789
  • 9 876-1789 from Counting Room
  • pasyuk@jlab.org

Run Plan: beamline commissioning

  • Make sure the following conditions are established: all CLAS12 detectors are off, both solenoid and torus magnets are off and target is empty.
  • Start the beamline commissioning following the instructions described in [1].
  • Record every relevant information in the logbook


Important Notes:

  1. During beam tune and harp scans Hall-B halo FSD must be masked.
  2. Do not run more than 60 minutes above 30 nA without the beam blocker in front of Faraday cup. Put beam blocker in for long running at high currents.
  3. If DAQ crashed/broken: Follow instruction on Documentation tab. If cannot resolved in 20-30 min call DAQ on-call cell phone.
  4. With any issue contact On-Call Experts or RC - do not spend more than 15-20 min trying to fix the problem.


General Instructions:

Locking up the hall

  • Work with the hall work coordinator (Doug Tilles or his designee) to make sure hall is ready for sweep at around 3pm:
    • Vacuum is good, magnet power supplies (Tagger and Torus) are turned ON and in remote mode, LCW is on.
  • Make sure experts, beamline, ECal, DC, HTCC, FTOF, and slow controls, checked their systems before the lockup.
  • When ready notify MCC to start sweep and lockup of the hall.
  • Make sure all necessary monitoring GUIs are up and running.
  • Make sure beam viewer screens are up.
  • When hall is in "Beam Permit"
    • Ramp torus to 10% of max current (380A)
    • Turn tagger magnet ON if beam tune on the tagger dump or tagger yoke dump will be needed (it will be needed if beam comes back after several hours of down)
    • Turn all beamline devices ON, turn all CLAS12 detectors OFF



Every Shift:

  1. Follow run plan as outlined by RC
  2. If any concern about beam stability, ask MCC if orbit locks are on (they should be).
  3. Keep shift summary up to date in HBLOG. Record all that happens.
    • Check on white board all scalers, strip charts and monitoring plots that need to be logged regularly
    • Document any beam condition change and send scaler GUIs to HBLOG
    • Fill out BTA hourly. Click "Load from EPICS" to automatically fill the left side.
    • Fill and submit the shift checklist in the logbook
  4. Perform 2H01A harp scan once per shift or when beam conditions have changed, based on beam monitors (BPMs, halo rates, beam-viewer). During harp scans the HV for DC and HTCC should be OFF.

Every Run:

  1. Log screenshots of:
    • main scaler GUI display
    • Detector occupancy plots
    • Trigger rate gui
    • Beam strip charts


Clas12design.png