RC Meeting: August 31st, 2020
The printable version is no longer supported and may have rendering errors. Please update your browser bookmarks and please use the default browser print function instead.
Back to Run Group F | Daily Run Group F Coordination Meetings
2020
March |
---|
19, 20, 21, 22, 23, 24 |
July |
31 |
August |
1, 2, 3, 4, 5, 6, 7, 8, 9, 10, 11, 12, 13, 14, 15, 16, 17, 18, 19, 20 21, 22, 23, 24, 25, 26, 27, 28, 29, 30, 31 |
September |
1, 2, 3, 4, 5, 6, 7, 8, 9, 10, 11, 12, 13, 14, 15, 16, 17, 18, 19, 20 21 |
RC:M. Hattawy
Summary of Aug. 31st
Owl shift
- Shift summary by the shift expert: https://logbooks.jlab.org/entry/3838117
- Issues: none
- Recorded data: 34M on D2
Day shift
- Shift summary by the shift expert: https://logbooks.jlab.org/entry/3838338
- Issues: beam down for 3.5 hours to do the pass change for HallC (failed because of some collimator in C).
- Studies: tuning the beam and Moller run 111: Polarization (%) 83.504 +/- 1.499
- Recorded data: 1.8 M on D2
Swing shift
- Shift summary by the shift expert:
- Issues:
- Recorded data:
Whole day summary
- Total recorded data today:
- Part-II total accumulated data on D2:
- Concerns:
Tomorrow daily RC meeting will be at usual time 12:00 PM using the link https://bluejeans.com/7576835804/