RC Meeting: September 12th, 2020
Jump to navigation
Jump to search
The printable version is no longer supported and may have rendering errors. Please update your browser bookmarks and please use the default browser print function instead.
Back to Run Group F | Daily Run Group F Coordination Meetings
2020
March |
---|
19, 20, 21, 22, 23, 24 |
July |
31 |
August |
1, 2, 3, 4, 5, 6, 7, 8, 9, 10, 11, 12, 13, 14, 15, 16, 17, 18, 19, 20 21, 22, 23, 24, 25, 26, 27, 28, 29, 30, 31 |
September |
1, 2, 3, 4, 5, 6, 7, 8, 9, 10, 11, 12, 13, 14, 15, 16, 17, 18, 19, 20 21 |
RC:M. Hattawy
Summary of Sep. 12th
Owl shift
- Shift summary by the shift expert: https://logbooks.jlab.org/entry/3 846352
- Issues: FCup high rates and fluctuating reading of the beam current. 3 hours of investigations, we will with it as is. masked the FCup tigger bit trigger.
- Recorded data: 28.6M on D2 (250 nA)
Day shift
- Shift summary by the shift expert: https://logbooks.jlab.org/entry/3846551
- Issues: none. Two hours beam down to replace Klystron in 1L17-2.
- Recorded data: 26M on D2
Swing shift
- Shift summary by the shift expert: https://logbooks.jlab.org/entry/3846731
- Issues: beam came back at 18:40, ECAL sector 5 power supply passed away at 22:30.
- Recorded data: 20M on D2
Whole day summary
- Total recorded data today: 75M on D2
- Part-II total accumulated data on D2: 1.783B
- Concerns: no more
Tomorrow daily RC meeting will be at usual time 12:00 PM using the link https://bluejeans.com/7576835804/