# Issues: 2L26 (down at 21:00 - 22:20)
 
# Issues: 2L26 (down at 21:00 - 22:20)
 
# Work: Opportunistic purge and final RG-F filling of D2 target gas.   
 
# Work: Opportunistic purge and final RG-F filling of D2 target gas.   
# Recorded data: 40M on D2
+
# Recorded data: 32M on D2 (+ 8M in ongoing 12937)
  
 
=== Whole day summary ===
 
=== Whole day summary ===

Revision as of 00:01, 20 September 2020

Back to Run Group F | Daily Run Group F Coordination Meetings


2020

March
19, 20, 21, 22, 23, 24
July
31
August
1, 2, 3, 4, 5, 6, 7, 8, 9, 10, 11, 12, 13, 14, 15, 16, 17, 18, 19, 20 21, 22, 23, 24, 25, 26, 27, 28, 29, 30, 31
September
1, 2, 3, 4, 5, 6, 7, 8, 9, 10, 11, 12, 13, 14, 15, 16, 17, 18, 19, 20 21

RC: M. Hattawy

Summary of Sep. 19th

Owl shift

  1. Shift summary by the shift expert: https://logbooks.jlab.org/entry/3851462
  2. Issues: DAQ crashes (~2 hours )
  3. Recorded data: 23M on D2 (+ 15M in ongoing run)

Day shift

  1. Shift summary by the shift expert: https://logbooks.jlab.org/entry/3851640
  2. Issues: none
  3. Recorded data: 45.5M on D2 (+8M in ongoing run passed to swing shift)

Swing shift

  1. Shift summary by the shift expert: https://logbooks.jlab.org/entry/3851784
  2. Issues: 2L26 (down at 21:00 - 22:20)
  3. Work: Opportunistic purge and final RG-F filling of D2 target gas.
  4. Recorded data: 32M on D2 (+ 8M in ongoing 12937)

Whole day summary

  1. Total recorded data today: 109M on D2.
  2. Part-II total collected data on D2: 2.261B triggers (75% of Part-II projected total data on D2)
  3. Concerns: none


Tomorrow daily RC meeting will be at usual time 12:00 PM using the link https://bluejeans.com/7576835804/