Summary of past 24h:

Thursday, August 6 to Friday, August 7

1-pass calibration run with inbending torus field

Completed

13 M events on He-4 target (7 M events at standard dRTPC HV settings, 6 M events with 30 V higher transfer voltage)


Plan for next 24 hours

5-pass beam setup and data taking.