Run Meeting: March 21st, 2020
Jump to navigation
Jump to search
The printable version is no longer supported and may have rendering errors. Please update your browser bookmarks and please use the default browser print function instead.
Back to Run Group F | Daily Run Group F Coordination Meetings
10:00AM Run Meeting, Counting house meeting room (200C)
RC: Carlos Ayerbe
Summary of past 24h:
- Summary in the RC Daily Report
https://logbooks.jlab.org/entry/3806850
- Hall was ready to sweep at ~12:10 (started at 12:50)
- Harp scans and beam quality ~4h total
- target full --> target empty
- Shunt installed for GEM3_Out
-------> RTPC HV <--------
- From MCC meeting (this morning)
- Stuart H. mentioned that we should be prepared to change to MEDCON6 (implying shutdown of the lab) given that many other labs started to shutdown.
- Stepan S. jumped with the question of how to proceed since, for instance, we need to run 1-pass for calibration purposes and it could imply some changes in the accelerator normal operation.
Plan:
- Run production
- Flush Target ~20:00 (or if there is an opportunistic beam down, close to this time)
- Time schedule changes accepted
Slides
Info
BlueJeans connection info:
To join the Meeting: https://bluejeans.com/7576835804