Difference between revisions of "10/13/2016 Meeting"
Line 9: | Line 9: | ||
'''1. Operations ''' | '''1. Operations ''' | ||
+ | LINAC | ||
+ | Problems with MO has stopped beam operations. | ||
+ | |||
CHL1 | CHL1 | ||
ESR_CHL Transferline utube installed | ESR_CHL Transferline utube installed | ||
− | Investigating capacity changes at CHL1 | + | Investigating capacity changes at CHL1. We seem to have less capacity now than one year ago. |
CHL2 | CHL2 | ||
Line 19: | Line 22: | ||
ESR | ESR | ||
Sending 15K 20g/s to Hall A target | Sending 15K 20g/s to Hall A target | ||
− | 4K load is at 1410W out of 1500W available | + | 4K load is at 1410W out of 1500W available from ESR alone. |
+ | |||
+ | Current Loads within approximately 50W | ||
+ | Hall A 6 magnets and one target | ||
+ | Hall B torus | ||
+ | Hall C Old HMS, HB, Q1 | ||
CTF | CTF |
Revision as of 07:52, 13 October 2016
Attendance
Creel, Wright, Dixon, Oren,
Agenda and Notes
1. Operations LINAC Problems with MO has stopped beam operations.
CHL1
ESR_CHL Transferline utube installed
Investigating capacity changes at CHL1. We seem to have less capacity now than one year ago.
CHL2 Normal
ESR Sending 15K 20g/s to Hall A target 4K load is at 1410W out of 1500W available from ESR alone.
Current Loads within approximately 50W Hall A 6 magnets and one target Hall B torus Hall C Old HMS, HB, Q1
CTF CMTF is testing the new quarter for M. Poelker VTA/CMTF is not using much capacity. We are getting questions from Larry Phillips about being able to supply liquid helium in dewars to the VTA so they can test during the plant shutdown and asked if we could return warm gas back to CHL.
HDR Water flow issues over weekend. Flow and supply pressure dropped for unknown reasons and lasted several hours and then self corrected.
2. Projects MSU