(Created page with " == Attendance == Thompson, Creel, Dixon, Oren, Michalski Wright doing utubes == Agenda and Notes == '''1. Operations ''' LINAC Magnet power supply repaired. A warm wi...")
 
 
(3 intermediate revisions by the same user not shown)
Line 3: Line 3:
 
== Attendance ==
 
== Attendance ==
  
Thompson, Creel, Dixon, Oren, Michalski
+
Thompson, Creel, Dixon, Oren, Michalski, Arenius
  
Wright doing utubes
+
Wright doing utubes on 2L07
  
 
== Agenda and Notes ==
 
== Agenda and Notes ==
Line 22: Line 22:
 
CHL1
 
CHL1
  
Recovery C8 failed completely. We are moving to complete new C8 and prepare it for installation. Work remaining is low and high side pressure tests which will be completed under the C9 TOSP as planned. Once pressure tests are complete the unit will be turned over to operations to install and clean carbon. In parallel EI&C will check out all the wiring and Alicia and Nate will work out a plan for installation to be approved by Mat when he returns. C8 pressure tests should happen today and then it will be turned over to OPS to install and bake carbon.
+
Old recovery C8 was removed and new C7 was installed yesterday. Piping and electrical work is expected to take about another week.
 +
 
  
 
CHL2
 
CHL2
Line 31: Line 32:
 
ESR
 
ESR
  
Sending 15K 20g/s to Hall A target
+
Hall C SHMS Q2 utubes installed yesterday. Cooldown will start today.
4K load is at 1410W out of 1500W available from ESR alone.
 
 
 
Current Loads within approximately 50W
 
Hall A 6 magnets and one target
 
Hall B torus (they have ramped to 300A and did a fast dump which blew the primary 4.5K relief)
 
Hall C Old HMS, HB, Q1
 
  
  
 
CTF
 
CTF
  
 
+
Plant operating normally.
The average fill rate w/cryomodule was 1.3 %/hr. 
 
The Dewar was idle for 52 hours.
 
The minimum Dewar Liquid Level was 69%.
 
The maximum Dewar Liquid Level was 95%.
 
 
 
Event(s):
 
1) October 19th, Cooling water piping modifications began.
 
 
2) October 21st, Swapped main compressors from C1 to C3
 
 
 
3) October 21st, Expander 1 valve arm was swapped
 
 
 
4) October 21st, Approx. 6 atm transferred from CHL
 
 
 
5) October 21st, arc cell (CCT20N) replaced and calibrated
 
 
 
6) October 23rd, Recovery Compressor C6 tripped on high discharge temp.
 
 
 
7) October 24, Expander 2A tripped off speed ratio and there was a breakthrough.
 
 
 
8) October 24th, Recovery Compressor C4 shut off. Load valve and coils replaced.
 
 
 
9) October 25th, C6 Acid Flush
 
 
 
10) October 25th, Approx. 2.8 atm transferred from CHL.
 
 
 
11) October 25th, main compressor low pressure suction alarm went off due to valve reaction time.
 
 
 
  
  
 
HDR
 
HDR
  
Normal
+
Plant operating normally.
  
  
Line 83: Line 50:
 
UITF
 
UITF
  
We can start performing work that is labor only.
+
Warm return VJ line section above cryomodule should be installed by COB Friday. Vacuum pump tie in was completed last week.
Work is starting on the VJ section of the HDIce warm return line that installs above the cryomodule and completing the vacuum pump connection point.
+
 
  
 
MSU
 
MSU
  
Upper cold box was delivered to MSU. Fabio wants us to change the model for the compressors from Ideas to Solidworks.  
+
2K Cold Box design work shifted over to Michael. Contractor on site installing cold box tie ins and platforms.  
  
  
 
LCLS2
 
LCLS2
  
Results of installation review were complicated. Reviewers wanted to see much more detail than they provided and have made several recommendations such as hiring an outside reviewer to check all calculations, verify piping sizes, etc.
+
Installation work for the cryo plant was officially moved to the SLAC team. The team is currently evaluating the bids on some of the utility support equipment. Bayonets etc. are complete and we are going to ship them to PHPK as soon as possible. Dana will advise when paperwork is done. The recovery compressor parts purchasing is underway. Work has begun on the frames.
 +
 
 +
LCLS2 safety people are visiting next week to ask questions on safety related items such as ODH, pressure systems, etc.
  
JLAB is moving ahead with fabrication of two recovery compressors and a guard vacuum skid.
 
  
  
 
'''3. Manpower '''
 
'''3. Manpower '''
  
The new EE regular employee and ECAD contract employee are scheduled to start on Nov 1.  
+
The new EE regular employee and ECAD contract employee started on Nov 1.  
  
We have an interview with Dr.  
+
We had an interview with Dr. Wang.
  
  
Line 108: Line 76:
  
 
1. Appraisals and new expectations
 
1. Appraisals and new expectations
2. Watch all spending on OPS and ENG accounts
+
 
 +
2. Watch spending on OPS and ENG accounts. Try to keep spending to critical "stop work" items.
  
  

Latest revision as of 10:15, 10 November 2016


Attendance

Thompson, Creel, Dixon, Oren, Michalski, Arenius

Wright doing utubes on 2L07

Agenda and Notes

1. Operations

LINAC

Magnet power supply repaired.

A warm window on 2L06 failed and required utubes to support repairs. 2L07 also ingested air into the beam line and now requires cryo cycling

The test plan to raise pressure in the linac failed on the first step and pressure was again lowered.


CHL1

Old recovery C8 was removed and new C7 was installed yesterday. Piping and electrical work is expected to take about another week.


CHL2

Normal


ESR

Hall C SHMS Q2 utubes installed yesterday. Cooldown will start today.


CTF

Plant operating normally.


HDR

Plant operating normally.


2. Projects

UITF

Warm return VJ line section above cryomodule should be installed by COB Friday. Vacuum pump tie in was completed last week.


MSU

2K Cold Box design work shifted over to Michael. Contractor on site installing cold box tie ins and platforms.


LCLS2

Installation work for the cryo plant was officially moved to the SLAC team. The team is currently evaluating the bids on some of the utility support equipment. Bayonets etc. are complete and we are going to ship them to PHPK as soon as possible. Dana will advise when paperwork is done. The recovery compressor parts purchasing is underway. Work has begun on the frames.

LCLS2 safety people are visiting next week to ask questions on safety related items such as ODH, pressure systems, etc.


3. Manpower

The new EE regular employee and ECAD contract employee started on Nov 1.

We had an interview with Dr. Wang.


4. Info from Will

1. Appraisals and new expectations

2. Watch spending on OPS and ENG accounts. Try to keep spending to critical "stop work" items.


4. Other

Gave STEM talks with LN2 demonstrations to three high school science classes this week.

Action Items

1. Must keep meeting to no more than 30 minutes


Action Item Updates