Thompson, Creel, Dixon, Oren, Michalski
+
Thompson, Creel, Dixon, Oren, Michalski, Arenius
  
Wright doing utubes
+
Wright doing utubes on 2L07
  
 
== Agenda and Notes ==
 
== Agenda and Notes ==
Line 61: Line 61:
  
 
Installation work for the cryo plant was officially moved to the SLAC team. The team is currently evaluating the bids on some of the utility support equipment. Bayonets etc. are complete and we are going to ship them to PHPK as soon as possible. Dana will advise when paperwork is done. The recovery compressor parts purchasing is underway. Work has begun on the frames.
 
Installation work for the cryo plant was officially moved to the SLAC team. The team is currently evaluating the bids on some of the utility support equipment. Bayonets etc. are complete and we are going to ship them to PHPK as soon as possible. Dana will advise when paperwork is done. The recovery compressor parts purchasing is underway. Work has begun on the frames.
 +
 +
LCLS2 safety people are visiting next week to ask questions on safety related items such as ODH, pressure systems, etc.
  
  
Line 74: Line 76:
  
 
1. Appraisals and new expectations
 
1. Appraisals and new expectations
2. Watch all spending on OPS and ENG accounts
+
 
 +
2. Watch spending on OPS and ENG accounts. Try to keep spending to critical "stop work" items.
  
  

Latest revision as of 10:15, 10 November 2016


Attendance

Thompson, Creel, Dixon, Oren, Michalski, Arenius

Wright doing utubes on 2L07

Agenda and Notes

1. Operations

LINAC

Magnet power supply repaired.

A warm window on 2L06 failed and required utubes to support repairs. 2L07 also ingested air into the beam line and now requires cryo cycling

The test plan to raise pressure in the linac failed on the first step and pressure was again lowered.


CHL1

Old recovery C8 was removed and new C7 was installed yesterday. Piping and electrical work is expected to take about another week.


CHL2

Normal


ESR

Hall C SHMS Q2 utubes installed yesterday. Cooldown will start today.


CTF

Plant operating normally.


HDR

Plant operating normally.


2. Projects

UITF

Warm return VJ line section above cryomodule should be installed by COB Friday. Vacuum pump tie in was completed last week.


MSU

2K Cold Box design work shifted over to Michael. Contractor on site installing cold box tie ins and platforms.


LCLS2

Installation work for the cryo plant was officially moved to the SLAC team. The team is currently evaluating the bids on some of the utility support equipment. Bayonets etc. are complete and we are going to ship them to PHPK as soon as possible. Dana will advise when paperwork is done. The recovery compressor parts purchasing is underway. Work has begun on the frames.

LCLS2 safety people are visiting next week to ask questions on safety related items such as ODH, pressure systems, etc.


3. Manpower

The new EE regular employee and ECAD contract employee started on Nov 1.

We had an interview with Dr. Wang.


4. Info from Will

1. Appraisals and new expectations

2. Watch spending on OPS and ENG accounts. Try to keep spending to critical "stop work" items.


4. Other

Gave STEM talks with LN2 demonstrations to three high school science classes this week.

Action Items

1. Must keep meeting to no more than 30 minutes


Action Item Updates