Line 12: Line 12:
  
 
   2 CHL Guard Vacuum
 
   2 CHL Guard Vacuum
     -Materials:  Ordered, expected on-site week of // 1/23
+
     -Materials:  Arrived.  Mechanical assembly is complete.
 
     -Pressure System:  Signed
 
     -Pressure System:  Signed
 
     -Drawings: Complete
 
     -Drawings: Complete
Line 21: Line 21:
 
   3 LN2 Dewar #1 instrumentation tubing replacement
 
   3 LN2 Dewar #1 instrumentation tubing replacement
 
     -Materials:  Ordered
 
     -Materials:  Ordered
     -Pressure System:  Back in DA review
+
     -Pressure System:  Signed
 
     -Drawings: Complete
 
     -Drawings: Complete
     -Fabrication: pending material/dpf
+
     -Fabrication: pending material
 
     -Operations: N/A
 
     -Operations: N/A
 
     -Testing:  To be initial service leak checked upon completion.
 
     -Testing:  To be initial service leak checked upon completion.
Line 33: Line 33:
 
     -Drawings: TBD
 
     -Drawings: TBD
 
     -Fabrication: TBD
 
     -Fabrication: TBD
     -Operations: All leaks have been identified and need to be tabulated and planned for repair/replacement.  
+
     -Operations: All leaks have been identified and tabulated.  Ops is investigating the repair of threaded connections.
     -Testing:  TBD
+
     -Testing:  Snoop
  
  
Line 47: Line 47:
  
 
   6 ESR ORS Carbon Replacement
 
   6 ESR ORS Carbon Replacement
     -Materials:  Need to be identified and ordered.
+
     -Materials:  Need to be identified and ordered.  Trying to find approval system for lifting adapters.
 
     -Pressure System:  N/A
 
     -Pressure System:  N/A
 
     -Drawings: Need to be developed.
 
     -Drawings: Need to be developed.
Line 55: Line 55:
  
 
   7 ESR 15K U-tube
 
   7 ESR 15K U-tube
     -Materials:  Being ordered
+
     -Materials:  ordered
     -Pressure System:  in review
+
     -Pressure System:  signed
 
     -Drawings: issued.
 
     -Drawings: issued.
 
     -Fabrication: awaiting materials
 
     -Fabrication: awaiting materials
Line 71: Line 71:
  
 
==ESR Status==
 
==ESR Status==
#Halls A, B, and C are cold and on cold return.
+
#Halls A, B, and C are on cold return. Hall C magnets filling. 
#Hall C is cooling SHMS Q3 to 100K.  U-tubes were stabbed Tuesday.
+
#Hall C is cooling SHMS Dipole to 100K.  U-tubes were stabbed Tuesday.
#Hall C will stab dipole u-tubes next week.
 
 
#Hall C target system is being cleaned.  Not connected to ESR or recovery as of now.
 
#Hall C target system is being cleaned.  Not connected to ESR or recovery as of now.
 
#CHL-ESR x-fer line will be in use occasionally over the next week.
 
#CHL-ESR x-fer line will be in use occasionally over the next week.
#T2 was warmed with no clear benefit. Developing actions to remedy the situation
+
#T2 will need to be stopped to facilitate simple trouble shooting on inlet valve/actuator.
  
 
==MSU FRIB==
 
==MSU FRIB==
Line 83: Line 82:
 
#IA complete
 
#IA complete
 
#GV complete
 
#GV complete
#LND awaiting confirmation of wind loading from thermax
+
#LND complete
 +
#waiting for examination docs from embler.

Revision as of 14:21, 1 February 2017

JLab

1/25 Update Organize cryo pressure systems

  • CHL:
  1 Replacement/upgrade of LN2 fill station gauging:
    -Materials: On-site
    -Pressure System:  Standard Maintenance
    -Drawings: N/A
    -Fabrication:  N/A
    -Operations:  Working.  Tank 2 complete.
    -Testing:  Snoop upon installation.
  2 CHL Guard Vacuum
    -Materials:  Arrived.  Mechanical assembly is complete.
    -Pressure System:  Signed
    -Drawings: Complete
    -Fabrication: N/A
    -Operations: N/A
    -Testing:  To be initial service leak checked upon completion of electrical work.  Pump temperatures will also need to be monitored.
  3 LN2 Dewar #1 instrumentation tubing replacement
    -Materials:  Ordered
    -Pressure System:  Signed
    -Drawings: Complete
    -Fabrication: pending material
    -Operations: N/A
    -Testing:  To be initial service leak checked upon completion.


  4 LN2 PBC leaks
    -Materials:  TBD
    -Pressure System:  TBD
    -Drawings: TBD
    -Fabrication: TBD
    -Operations: All leaks have been identified and tabulated.  Ops is investigating the repair of threaded connections.
    -Testing:  Snoop


  5 CHL Recovery Purifier Sieve replacement
    -Materials:  on-site
    -Pressure System:  N/A
    -Drawings: N/A
    -Fabrication: N/A
    -Operations: P5 sieve replaced and being cleaned.
    -Testing:  N/A


  6 ESR ORS Carbon Replacement
    -Materials:  Need to be identified and ordered.  Trying to find approval system for lifting adapters.
    -Pressure System:  N/A
    -Drawings: Need to be developed.
    -Fabrication: awaiting drawings
    -Operations: Needs to be scheduled/planned. 
    -Testing:  Snoop at joints.  Spool pieces will need to be tested.
  7 ESR 15K U-tube
    -Materials:  ordered
    -Pressure System:  signed
    -Drawings: issued.
    -Fabrication: awaiting materials
    -Operations: U-tube will be stabbed at earliest convenience
    -Testing:  pressure test per DPF
  8 ESR Oil collection
    -Materials:  TBD
    -Pressure System:  TBD
    -Drawings: TBD
    -Fabrication: TBD
    -Operations: May require piping removal or plant shutdown
    -Testing:  not likely. category D piping at most.

ESR Status

  1. Halls A, B, and C are on cold return. Hall C magnets filling.
  2. Hall C is cooling SHMS Dipole to 100K. U-tubes were stabbed Tuesday.
  3. Hall C target system is being cleaned. Not connected to ESR or recovery as of now.
  4. CHL-ESR x-fer line will be in use occasionally over the next week.
  5. T2 will need to be stopped to facilitate simple trouble shooting on inlet valve/actuator.

MSU FRIB

Organize and publish pressure system documentation for pressure systems. Actions are as listed in the summary document.

  1. IA complete
  2. GV complete
  3. LND complete
  4. waiting for examination docs from embler.