(Created page with " == Attendance == Thompson, Creel, Dixon, Michalski, Oren, Arenius is on his way back from Ohio == Agenda and Notes == '''1. Operations ''' LINAC Normal CHL1 Repea...")
 
 
Line 103: Line 103:
 
== Action Item Updates ==
 
== Action Item Updates ==
 
1. We are going to start preliminary design of the 2K cold box replacement.
 
1. We are going to start preliminary design of the 2K cold box replacement.
 +
 +
2. Investigate possibility of buying another welder (<$6K)

Latest revision as of 10:01, 2 February 2017

Attendance

Thompson, Creel, Dixon, Michalski, Oren,

Arenius is on his way back from Ohio


Agenda and Notes

1. Operations

LINAC

Normal


CHL1

Repeated intermittent problems with SC1 CC1 magnetic bearing cabinet. We are investigating.


CHL2

Normal


ESR

Normal.

Halls are using maximum capacity of the ESR. Use of the transerline is dependent on the issues at CHl1.


CTF

Normal


HDR

Normal.

Operators did notice that each time the magnet is ramped the vacuum softens in coil #2 and #4. Seems to be normal for the system. Might be related to the change in lead flow effecting localized nitrogen ice sublimation because of the known LN2 to vacuum space leaks on these two magnets.


2. Projects


UIM

Shutdown scheduled for Feb 17. We are finalizing the detailed daily work plan.


UITF


MSU

Working to accumulate the pressure systems documentation. Concerns over information sharing.


LCLS2

Cold compressor review in France went well. Only real surprise was the seismic results forced the manufacturer to increase the thickness of the base plates. Smith Group is an A&E firm to help SLAC put together the installation package. SLAC will not be able to get an installation contract in place until ~Sep even though equipment begins arriving in Apr.


Korea

Review went fine. They are still interested in a collaboration


3. Manpower

New engineer arriving mid Feb. He will work 75% of his time on EI&C for LCLS2 and remainder on OPS.



4. Info from Will

1. LN2 contract proposals are in.

2. New director starts Apr 3.

4. Funding could impact summer shutdown schedule possibly forcing the shutdown of CHL2 earlier than the May bill read. Possibly as early as 23 March. We are moving ahead with electrical installation and fabrication of the piping spools for this job.


5. Other

Action Items

1. Must keep meeting to no more than 30 minutes

2. Plan the replacement of the SC2 power feedthrus.


Action Item Updates

1. We are going to start preliminary design of the 2K cold box replacement.

2. Investigate possibility of buying another welder (<$6K)