Difference between revisions of "02/07/2017 Coordination Meeting"

From Cryowiki
Jump to navigationJump to search
Line 23: Line 23:
  
  
'''3. Recent History '''
+
'''3. ESR2 Upgrade '''
 +
 
 +
Cryogenics group has been pushing the installation of the ESR2 4KW at 4.5K SSC plant for many years. It keeps getting bumped because of funding.
  
  

Revision as of 16:43, 6 February 2017

Attendance

Creel, Wright, Schleeper, Fair, Kashy, Bridza, Lassiter, Kepple, Fansler, Gomez, Oren

Agenda and Notes

This meeting is to discuss the ESR capacity usage by the Halls.


1. ESR History

Plant originally built in 1978 for the LBL ESCAR Project. It operated < 900 hours before being shutdown.

Plant was moved to JLAB and installed in 1994 JLAB to support Hall's A, B, and C. The plant has been in nearly continuous operation for 22 years.


2. ESR Capacity

Plant capacity envelope (1500W at 4.5K) OR (800W at 4.5K PLUS 1200W at 15K)

Additional transient capacity available from CHL via transferline of up to 20g/s at 4.5K


3. ESR2 Upgrade

Cryogenics group has been pushing the installation of the ESR2 4KW at 4.5K SSC plant for many years. It keeps getting bumped because of funding.


4. Plan Forward

Action Items

1. Finish the ESR2 design, fabrication, and commissioning ... quickly.