==JLab==
 
==JLab==
1/25 Update
+
2/13 Update
 
Organize cryo pressure systems
 
Organize cryo pressure systems
 
* CHL:
 
* CHL:
Line 12: Line 12:
  
 
   2 CHL Guard Vacuum
 
   2 CHL Guard Vacuum
     -Materials:  Arrived.  Mechanical assembly is complete.
+
     -Materials:  installed
 
     -Pressure System:  Signed
 
     -Pressure System:  Signed
 
     -Drawings: Complete
 
     -Drawings: Complete
Line 42: Line 42:
 
     -Drawings: N/A
 
     -Drawings: N/A
 
     -Fabrication: N/A
 
     -Fabrication: N/A
     -Operations: P5 sieve replaced and being cleaned.
+
     -Operations: P5 sieve replaced and ready for use.
 
     -Testing:  N/A
 
     -Testing:  N/A
  
  
 
   6 ESR ORS Carbon Replacement
 
   6 ESR ORS Carbon Replacement
     -Materials:  Need to be identified and ordered.  Trying to find approval system for lifting adapters.
+
     -Materials:  Need to be identified and ordered.  Rusty sprouse reviewing lifting adapter.
 
     -Pressure System:  N/A
 
     -Pressure System:  N/A
 
     -Drawings: Need to be developed.
 
     -Drawings: Need to be developed.
Line 58: Line 58:
 
     -Pressure System:  signed
 
     -Pressure System:  signed
 
     -Drawings: issued.
 
     -Drawings: issued.
     -Fabrication: awaiting materials
+
     -Fabrication: in fabrication
 
     -Operations: U-tube will be stabbed at earliest convenience
 
     -Operations: U-tube will be stabbed at earliest convenience
 
     -Testing:  pressure test per DPF
 
     -Testing:  pressure test per DPF
Line 69: Line 69:
 
     -Operations: May require piping removal or plant shutdown
 
     -Operations: May require piping removal or plant shutdown
 
     -Testing:  not likely. category D piping at most.
 
     -Testing:  not likely. category D piping at most.
 +
 +
 +
  9 CHL IA modification
 +
    -Materials:  ordered
 +
    -Pressure System:  TBD
 +
    -Drawings: in development
 +
    -Fabrication: TBD
 +
    -Operations: N/A
 +
    -Testing:  Initial service leak test
  
 
==ESR Status==
 
==ESR Status==

Revision as of 14:58, 13 February 2017

JLab

2/13 Update Organize cryo pressure systems

  • CHL:
  1 Replacement/upgrade of LN2 fill station gauging:
    -Materials: On-site
    -Pressure System:  Standard Maintenance
    -Drawings: N/A
    -Fabrication:  N/A
    -Operations:  Working.  Tank 2 complete.
    -Testing:  Snoop upon installation.
  2 CHL Guard Vacuum
    -Materials:  installed
    -Pressure System:  Signed
    -Drawings: Complete
    -Fabrication: N/A
    -Operations: N/A
    -Testing:  To be initial service leak checked upon completion of electrical work.  Pump temperatures will also need to be monitored.
  3 LN2 Dewar #1 instrumentation tubing replacement
    -Materials:  Ordered
    -Pressure System:  Signed
    -Drawings: Complete
    -Fabrication: pending material
    -Operations: N/A
    -Testing:  To be initial service leak checked upon completion.


  4 LN2 PBC leaks
    -Materials:  TBD
    -Pressure System:  TBD
    -Drawings: TBD
    -Fabrication: TBD
    -Operations: All leaks have been identified and tabulated.  Ops is investigating the repair of threaded connections.
    -Testing:  Snoop


  5 CHL Recovery Purifier Sieve replacement
    -Materials:  on-site
    -Pressure System:  N/A
    -Drawings: N/A
    -Fabrication: N/A
    -Operations: P5 sieve replaced and ready for use.
    -Testing:  N/A


  6 ESR ORS Carbon Replacement
    -Materials:  Need to be identified and ordered.  Rusty sprouse reviewing lifting adapter.
    -Pressure System:  N/A
    -Drawings: Need to be developed.
    -Fabrication: awaiting drawings
    -Operations: Needs to be scheduled/planned. 
    -Testing:  Snoop at joints.  Spool pieces will need to be tested.
  7 ESR 15K U-tube
    -Materials:  ordered
    -Pressure System:  signed
    -Drawings: issued.
    -Fabrication: in fabrication
    -Operations: U-tube will be stabbed at earliest convenience
    -Testing:  pressure test per DPF
  8 ESR Oil collection
    -Materials:  TBD
    -Pressure System:  TBD
    -Drawings: TBD
    -Fabrication: TBD
    -Operations: May require piping removal or plant shutdown
    -Testing:  not likely. category D piping at most.


  9 CHL IA modification
    -Materials:  ordered
    -Pressure System:  TBD
    -Drawings: in development
    -Fabrication: TBD
    -Operations: N/A
    -Testing:  Initial service leak test

ESR Status

  1. Halls A, B, and C are on cold return. Hall C magnets filling.
  2. Hall C is cooling SHMS Dipole to 100K. U-tubes were stabbed Tuesday.
  3. Hall C target system is being cleaned. Not connected to ESR or recovery as of now.
  4. CHL-ESR x-fer line will be in use occasionally over the next week.
  5. T2 will need to be stopped to facilitate simple trouble shooting on inlet valve/actuator.

MSU FRIB

Organize and publish pressure system documentation for pressure systems. Actions are as listed in the summary document.

  1. IA complete
  2. GV complete
  3. LND complete
  4. waiting for examination docs from embler.