==JLab==
 
==JLab==
1/25 Update
+
3/15 Update
Organize cryo pressure systems
+
 
 
* CHL:
 
* CHL:
   # Replacement/upgrade of LN2 fill station gauging:
+
   1 Replacement/upgrade of LN2 fill station gauging:
     -Materials: On-site
+
     -Gauges have been replaced but the Dewar #1 Gauge is reading incorrectly. Working to repair.
    -Pressure System:  Standard Maintenance
 
    -Drawings: N/A
 
    -Fabrication:  N/A
 
    -Operations: Working.  Tank 2 complete.
 
    -Testing:  Snoop upon installation.
 
  
   # CHL Guard Vacuum
+
   2 CHL Guard Vacuum
     -Materials:  Ordered, expected on-site week of // 1/23
+
     -Materials:  installed
 
     -Pressure System:  Signed
 
     -Pressure System:  Signed
 
     -Drawings: Complete
 
     -Drawings: Complete
     -Fabrication: N/A
+
     -Fabrication: Removal/repair of the hand rail.  Grouting and leg re-work.
     -Operations: N/A
+
     -Operations: Will need to remove feet, grout, shim and anchor the feet.  Will require welding.
 
     -Testing:  To be initial service leak checked upon completion of electrical work.  Pump temperatures will also need to be monitored.
 
     -Testing:  To be initial service leak checked upon completion of electrical work.  Pump temperatures will also need to be monitored.
  
   # LN2 Dewar #1 instrumentation tubing replacement
+
   3 LN2 Dewar #1 instrumentation tubing replacement
     -Materials:  Ordered
+
     -Materials:  On-site
     -Pressure System:  Back in DA review
+
     -Pressure System:  Signed
 
     -Drawings: Complete
 
     -Drawings: Complete
     -Fabrication: pending material/dpf
+
     -Fabrication: All paperwork and materials are with Scott.  He is scheduling.
 
     -Operations: N/A
 
     -Operations: N/A
     -Testing:  To be initial service leak checked upon completion.
+
     -Testing:  To be initial service leak checked upon completion.
  
  
   # LN2 PBC leaks
+
   4 LN2 PBC leaks
 
     -Materials:  TBD
 
     -Materials:  TBD
 
     -Pressure System:  TBD
 
     -Pressure System:  TBD
 
     -Drawings: TBD
 
     -Drawings: TBD
 
     -Fabrication: TBD
 
     -Fabrication: TBD
     -Operations: All leaks have been identified and need to be tabulated and planned for repair/replacement.  
+
     -Operations: All leaks have been identified and tabulated.  Ops is investigating the repair of threaded connections.
     -Testing:  TBD
+
     -Testing:  Snoop
  
  
   # CHL Recovery Purifier Sieve replacement
+
   5 ESR ORS Carbon Replacement
     -Materials:  on-site
+
     -Materials:  Lifting adapter approved by Sprouse.  Estimating ~$350 for materials
 
     -Pressure System:  N/A
 
     -Pressure System:  N/A
     -Drawings: N/A
+
     -Drawings: Need to be developed.  Sent to Corey for him to prioritize.
     -Fabrication: N/A
+
     -Fabrication: awaiting drawings
     -Operations: P5 sieve replaced and being cleaned.
+
     -Operations: Needs to be scheduled/planned. Probably next summer
     -Testing:  N/A
+
     -Testing:  Spool pieces will need to be tested.
  
  
   # ESR ORS Carbon Replacement
+
   6 ESR Oil collection
     -Materials:  Need to be identified and ordered.
+
     -Materials:  Ordered, waiting on sight glass to arrive.
 
     -Pressure System:  N/A
 
     -Pressure System:  N/A
     -Drawings: Need to be developed.
+
     -Drawings: Sketch delivered to shop.
     -Fabrication: awaiting drawings
+
     -Fabrication: TBD
     -Operations: Needs to be scheduled/planned.  
+
     -Operations: Will require familiarity with system prior to installation.
     -Testing:  Snoop at joints.  Spool pieces will need to be tested.
+
     -Testing:  N/A, down stream of relief.
  
  # ESR 15K U-tube
 
    -Materials:  Being ordered
 
    -Pressure System:  in review
 
    -Drawings: issued.
 
    -Fabrication: awaiting materials
 
    -Operations: U-tube will be stabbed at earliest convenience
 
    -Testing:  pressure test per DPF
 
  
   # ESR Oil collection
+
   7 CHL IA modification
     -Materials:  TBD
+
     -Materials:  ordered
     -Pressure System:  TBD
+
     -Pressure System:  Cat D
     -Drawings: TBD
+
     -Drawings: in development
 
     -Fabrication: TBD
 
     -Fabrication: TBD
     -Operations: May require piping removal or plant shutdown
+
     -Operations: N/A
     -Testing:  not likely. category D piping at most.
+
     -Testing:  Initial service leak test
 +
 
 +
  8 NL Cool Down Tie-in
 +
    -Will purge and tie-in cool down valve
  
 
==ESR Status==
 
==ESR Status==
-Halls A, B, and C are cold and on cold return.
+
#Hall A:
-Hall C is cooling SHMS Q3 to 100K.  U-tubes were stabbed Tuesday.
+
  - Magnets cold, on cold return, controlling properly
-Hall C will stab dipole u-tubes next week.
+
  - Warm flows return to CHL
-Hall C target system is being cleaned.  Not connected to ESR or recovery as of now.
+
  - Lead flows minimal
-CHL-ESR x-fer line will be in use occasionally over the next week.
+
  - Target cold (~300W).
-T2 was warmed with no clear benefit.  Developing actions to remedy the situation
+
 
 +
#Hall B:K
 +
  - Torus at 80K
 +
  - Warm flows return to CHL
 +
  - Solenoid scheduled for August delivery
 +
  - Buffer dewar cool down started
  
==MSU FRIB==
+
#Hall C:
Organize and publish pressure system documentation for pressure systems. Actions are as listed in the summary document.
+
  - All magnets cold, on cold return
 +
  - Warm flows return to CHL
 +
  - Return transfer line replacement did not alleviate magnet pressure issue.
 +
  - Target cold.

Latest revision as of 12:21, 16 March 2017

JLab

3/15 Update

  • CHL:
  1 Replacement/upgrade of LN2 fill station gauging:
    -Gauges have been replaced but the Dewar #1 Gauge is reading incorrectly.  Working to repair.
  2 CHL Guard Vacuum
    -Materials:  installed
    -Pressure System:  Signed
    -Drawings: Complete
    -Fabrication: Removal/repair of the hand rail.  Grouting and leg re-work.
    -Operations: Will need to remove feet, grout, shim and anchor the feet.  Will require welding.
    -Testing:  To be initial service leak checked upon completion of electrical work.  Pump temperatures will also need to be monitored.
  3 LN2 Dewar #1 instrumentation tubing replacement
    -Materials:  On-site
    -Pressure System:  Signed
    -Drawings: Complete
    -Fabrication: All paperwork and materials are with Scott.  He is scheduling.
    -Operations: N/A
    -Testing:  To be initial service leak checked upon completion.  


  4 LN2 PBC leaks
    -Materials:  TBD
    -Pressure System:  TBD
    -Drawings: TBD
    -Fabrication: TBD
    -Operations: All leaks have been identified and tabulated.  Ops is investigating the repair of threaded connections.
    -Testing:  Snoop


  5 ESR ORS Carbon Replacement
    -Materials:  Lifting adapter approved by Sprouse.  Estimating ~$350 for materials
    -Pressure System:  N/A
    -Drawings: Need to be developed.  Sent to Corey for him to prioritize.
    -Fabrication: awaiting drawings
    -Operations: Needs to be scheduled/planned.  Probably next summer
    -Testing:  Spool pieces will need to be tested.


  6 ESR Oil collection
    -Materials:  Ordered, waiting on sight glass to arrive.
    -Pressure System:  N/A
    -Drawings: Sketch delivered to shop.
    -Fabrication: TBD
    -Operations: Will require familiarity with system prior to installation.
    -Testing:  N/A, down stream of relief.


  7 CHL IA modification
    -Materials:  ordered
    -Pressure System:  Cat D
    -Drawings: in development
    -Fabrication: TBD
    -Operations: N/A
    -Testing:  Initial service leak test
  8 NL Cool Down Tie-in
    -Will purge and tie-in cool down valve

ESR Status

  1. Hall A:
 - Magnets cold, on cold return, controlling properly
 - Warm flows return to CHL
 - Lead flows minimal
 - Target cold (~300W).
  1. Hall B:K
 - Torus at 80K
 - Warm flows return to CHL
 - Solenoid scheduled for August delivery
 - Buffer dewar cool down started
  1. Hall C:
 - All magnets cold, on cold return
 - Warm flows return to CHL
 - Return transfer line replacement did not alleviate magnet pressure issue.
 - Target cold.