Difference between revisions of "05/02/2017 Meeting"

From Cryowiki
Jump to navigationJump to search
 
(2 intermediate revisions by one other user not shown)
Line 13: Line 13:
 
1. Safety
 
1. Safety
  
We had an incident where an individual was working in the SBR compressor room and tripped over installed piping and injured his leg. His injury required stitches and is a recordable event.
+
No issues.
  
  
Line 23: Line 23:
 
3. Operations (A brief description of the highlights for the past week at CHL's, ESR, HDR, CTF)
 
3. Operations (A brief description of the highlights for the past week at CHL's, ESR, HDR, CTF)
  
CTF is operating. Team is working on reassembling the K2.
+
CTF is operating. The LCLS2 cryomodule was recooled and testing resumed. A team is working on reassembling the K2. Work continues on the CB #3 installation.
  
ESR normal.
+
ESR normal. Hall is recooling the last magnet this week.
  
 
CHL1 at 4K
 
CHL1 at 4K
Line 31: Line 31:
 
CHL2 is off to support C6 work.
 
CHL2 is off to support C6 work.
  
CHL Recovery: Purifier 5 carbon has been replaced. pump and backfills on-going. After purifier 5 is online and operating acceptably, carbon will be replaced in bed #4.
+
CHL Recovery: We are continuing to work on the purifier problem.
  
 
HDR Normal
 
HDR Normal
Line 39: Line 39:
  
 
CHL1 SC1 CC5
 
CHL1 SC1 CC5
 
Final utubes for disconnecting SC1 are to be done Wed and Thur.
 
 
Air Liquide is expecting to have technician here on site first or second week of May.
 
 
Decisions need to be made regarding the flanging/sealing of the CC.
 
 
  
 
UIM (Wijeratne, Wright, Creel)
 
UIM (Wijeratne, Wright, Creel)
  
Calendar
+
Cold box #3 commissioning is underway.
 
 
The shutdown is scheduled from 17 Feb - 9 Apr (Dewar Full). We are in clean up mode anticipating restart around Thursday..
 
Anticipate problems with the controls during the cooldown.
 
  
  
Line 58: Line 48:
  
 
'''Kinney Pump Relocation'''
 
'''Kinney Pump Relocation'''
- Detailed design of Kinney suction and discharge piping system was completed.  
+
* Detailed design of Kinney suction and discharge piping system was completed.  
- The material for Kinney suction has been received. The material for Kinney discharge has ordered.
+
* The material for Kinney suction has been received. The material for Kinney discharge has ordered.
- Started the detailed design package of the cooling water system.  
+
* Started the detailed design package of the cooling water system.  
- The actual design hours have been over the budget. This is mainly because:
+
* The actual design hours have been over the budget. This is mainly because:
 
   1. The modification of the existing Coalescers piping system was not initially budgeted.
 
   1. The modification of the existing Coalescers piping system was not initially budgeted.
 
   2. More efforts were put on the design in order to meet the clearness requirement of the control panel.
 
   2. More efforts were put on the design in order to meet the clearness requirement of the control panel.
Line 68: Line 58:
  
 
'''Gas Management System'''
 
'''Gas Management System'''
- 35% concept planning has been completed.
+
* 35% concept planning has been completed.
- The 3D model was done based on the concept design.
+
* The 3D model was done based on the concept design.
- All pneumatic control valves have been ordered.
+
* All pneumatic control valves have been ordered.
 
    
 
    
  

Latest revision as of 11:00, 2 May 2017

Attendance

Thompson, Creel, ,Radovic, Dixon, Wright, Butler, Radovic, Wijeratne, Norton, Saringer, Schleeper, Yang, Perry, Laverdure


Goals

The purpose of this weekly meeting is to discuss plant operations and group projects with the cryogenics group managers and supervisors. During this meeting we will discuss ongoing and future projects, priorities, manpower, schedules, expenditures, and problems.


Agenda and Notes

1. Safety

No issues.


2. Schedule

   Near term schedule Media:img_3327.jpg


3. Operations (A brief description of the highlights for the past week at CHL's, ESR, HDR, CTF)

CTF is operating. The LCLS2 cryomodule was recooled and testing resumed. A team is working on reassembling the K2. Work continues on the CB #3 installation.

ESR normal. Hall is recooling the last magnet this week.

CHL1 at 4K

CHL2 is off to support C6 work.

CHL Recovery: We are continuing to work on the purifier problem.

HDR Normal


4. JLAB Internal Group Projects

CHL1 SC1 CC5

UIM (Wijeratne, Wright, Creel)

Cold box #3 commissioning is underway.


GPP (Yang, Wright)

Kinney Pump Relocation

  • Detailed design of Kinney suction and discharge piping system was completed.
  • The material for Kinney suction has been received. The material for Kinney discharge has ordered.
  • Started the detailed design package of the cooling water system.
  • The actual design hours have been over the budget. This is mainly because:
 1. The modification of the existing Coalescers piping system was not initially budgeted.
 2. More efforts were put on the design in order to meet the clearness requirement of the control panel.
 3. The girder and other components near the piping system had to be modeled after interference between the piping and structure components were found.
 4. The design of the piping support was much more than originally estimated.

Gas Management System

  • 35% concept planning has been completed.
  • The 3D model was done based on the concept design.
  • All pneumatic control valves have been ordered.


CHL2 C6 (Perry, Creel)

C6 installation work has started. Mechanics are working now. Electrical should finish by the end of the week. We are expecting about 4 more weeks of work to complete installation then commissioning will start.


JLAB Guard Vac (Schleeper, Radovic)

-Legs are being cut and prepped for anchor/grout. DONE! -Taps need to be added to the pump suction. (fab) IP -remove/route the conduit (Electrical) -remove railing (ops) -Instrument Air line (fab) -final assembly of pump/filters (ops) -controls (electrical)


CHL LN2 Dewar Fill Transfer line (Schleeper)

-process improvements being tested -vacuum needs to be pumped -relief valve needs to be replaced/ordered (will set up a meeting)


JLAB 3rd Recovery Compressor (Saringer)

The skid is complete. We are purchasing a pneumatic actuator to install on one of the existing compressor suction valves to see if it prevents oil migration problems.


JLAB recovery header rework (Saringer, Wright)

Job is being re-planned to shrink the required down time and cost.


JLAB Vaporizer (Perry, Wright)

We have most of the parts. The installation is on hold. It might be used as a filler job if things ever get light. Robert will check if there is any instrumentation and controls associated.


CHL to FEL Utubes (Perry, Corey)

If a designer becomes available they will be placed on this project. It is currently in Craig's queue.


CHL LN2 Fill Relief Replacement (Schleeper, Thompson) Replacing existing relief valve. Evaluate fill process to prevent lifting the relief.


CHL LN2 Dewar Instrumentation Replacement (Schleeper, Thompson) causing errors in the pressure gauge on fill station.

CHL LN2 Pressure Building Coil leaks (Schleeper, Thompson, Hunewill)

ESR Carbon Replacement (Schleeper, Butler)

ESR Oil Containment (Schleeper, Thompson), working. Paused to support C6 work.

CHL1 Regeneration Skid Removal (Schleeper, Thompson)

5. JLAB External Group Projects

Hall B 12GeV (Thompson)

We have been tasked with fabricating flex lines for the solenoid can. It will take approximately 4 months. (Jay). Roland is continuing to work with Ruben on solenoid can instrumentation as needed.

Solenoid is expected 12 May ????.


UITF (Perry, Radovic)

Thermosiphon and utubes are being fabricated. The electrical controls work will start after the UIM CTF & C6 are finished.


CHL2 Main Compressor Oil Level Alarms (Saringer, Wright)

We are having trouble managing compressor oil levels especially when there are large ambient temperature changes. We need to work on a solution. Drawings are done but waiting for approval.


NL cooldown header re-connection (Schleeper, Wright)

There is some concern that moisture may still exist within the cool down piping in the north linac. The goal is to have a hygrometer added to the recovery system so that when a purge flow is added, moisture can be monitored. After the cool down piping has been purged (duration TBD), we will re-connect the cool down line at the conflats. Delayed due to purifier issues.


SRF is planning to replace cold windows on 15 modules

Ongoing.


6. JLAB External Projects

MSU (Dixon)

Robert is still working 2K controls.


LCLS2 (Dixon)

We are building two recovery compressors. Due in July 17'. (Issac) We are building a guard vac skid for LCLS2. Not started. Due end of October 17'(Issac). We might also fabricate a water skid. FDR for 2K cold box Mar 9.

LCLS2 is indicating we could pick and choose a host of items we could build for them such as 230 bayonets in approximately 6-7 months.

Repair of EV245RT Coming up with preliminary design for applying force without an EV.

Inspection of Relief Devices per Pressure System's Requirement: Started CTF and CHL2.


7. Summer Maintenance Work Plan (Wright, Creel)

PRIORITY

CHL1 and CHL2 electrical maintenance including controls

GPP CTF gas management skid and Kinney piping move (engineering/design $$, parts $$$, labor $$$)

CHL1 regen skid disconnect (engineering/design 0, parts 0, labor $)


Add e-stop guards on all systems (engineering/design $, parts $, labor $)

SC1 Vacuum Controls (engineering/design 0, parts 0, labor $)

CHL1 C3 - Load Valve Readback and Power-meter (engineering/design ?, parts ?, labor ?) - Can be done anytime

CHL1 C6 - Load Valve Readback Calibration (engineering/design 0, parts 0, labor $) - Can be done anytime

CHL2 MCS2 Retighten Flexitalic Gaskets per torque spec. (engineering/design 0, parts 0, labor $)

CHL Hurricane Relief System - EV for SLinac not functional (engineering/design ?, parts ?, labor ?)


POSSIBLE

CHL1 MCB CAMAC to PLC conversion (engineering/design $, parts $, labor $$$)

CHL1 MCB1 Vacuum - Controls and Equipment (engineering/design $, parts $$$, labor $)


NOT POSSIBLE

CHL2 SC2 cold compressor power feedthru replacement (engineering/design 0, parts 0, labor $$)

CHL1 vaporizer cold piping (engineering/design 0, parts 0, labor $$$)

Spare utubes for c50 and c100 (engineering/design 0, parts $$, labor $$)

CHL/FEL shield utube (engineering/design $, parts $, labor $)

CHL Purifier LN2 Solenoid Replacement (engineering/design 0, parts $, labor $) - Can be done anytime

CHL1 MCB1 - MCS1 Rusty Flange, Bolt Change-out (engineering/design 0, parts 0, labor $)

SBR CBX Isolation (engineering/design $, parts $, labor $$??)

SBR C1/C2 - Install Current Transducer (engineering/design ?, parts ?, labor ?)

SBR C1 - Loading itself (engineering/design ?, parts ?, labor ?) - Can be done anytime

ESR-TL (EV11139) Valve Re-build (engineering/design 0, parts $, labor $)

CHL Recovery 10DR Valve - dismantle, header inspection (engineering/design 0, parts $/2, labor $)

CHL2 SCW Solenoid with Spools ((engineering/design $, parts $, labor $) - SV Ordered Already

CHL2 GN2 Vent Piping (engineering/design 0, parts 0, labor $)

CHL2 UCBX/LCBX backup vacuum - connect to K100 vacuum skid (engineering/design $, parts $, labor $)

CHL2 MCS2 - Replace valve on Purifier Discharge Header (engineering/design $, parts $, labor $) - Valve already bought.


8. Long Range Plans (Wright, Creel)

Jobs we are considering in no particular order

ESR gas management carbon bed maintenance (engineering/design $, parts $, labor $$)

ESR CAMAC to PLC conversion (engineering/design $$$, parts $$$, labor $$$)

? Action Items

1.

2. Before next meeting the persons whose name appears beside an item will write a short update.

3. Complete summer maintenance list

4. Need to start thinking about a new 2K cold box design using FRIB/LCLS2 cold compressor designs.

5. Need to start pushing the engineering/design effort forward for the ESR2 plant.


Action Item Updates

1.