Difference between revisions of "Meeting Oct 14, 2016"
(Created page with "== Attendance == Creel, Wright, S. Thompson, Wijeratne == Agenda and Notes == '''1. Schedule ''' '''2. Manpower ''' '''3. Drawings ''' == Action Items == 1.") |
|||
Line 2: | Line 2: | ||
Creel, Wright, S. Thompson, Wijeratne | Creel, Wright, S. Thompson, Wijeratne | ||
+ | |||
+ | == Summary for Meeting == | ||
+ | Installation of the UIM cold box is one of the labs highest priorities. It must be completed. We are to implement all measures to complete the work ahead of schedule. The shutdown of the testlabs testing schedule is a major hit to the lab and we need to be creative and find ways to do it efficiently. | ||
Line 8: | Line 11: | ||
'''1. Schedule ''' | '''1. Schedule ''' | ||
+ | |||
+ | |||
Line 18: | Line 23: | ||
== Action Items == | == Action Items == | ||
− | 1. | + | 1. Need Mat, Thilan, and Scott to sit down and review all of the remaining work and come up with a detailed plan that will allow us to track the project closer. |
+ | |||
+ | 2. Crew progress must be checked daily by the fab shop supervisor and project engineer against the expectations and adjustments made immediately. The group leader will also start making spot checks on the job using the schedule as a map. | ||
+ | |||
+ | |||
+ | 3. We will implement longer shifts or two shifts everywhere possible. |
Latest revision as of 08:48, 14 October 2016
Attendance
Creel, Wright, S. Thompson, Wijeratne
Summary for Meeting
Installation of the UIM cold box is one of the labs highest priorities. It must be completed. We are to implement all measures to complete the work ahead of schedule. The shutdown of the testlabs testing schedule is a major hit to the lab and we need to be creative and find ways to do it efficiently.
Agenda and Notes
1. Schedule
2. Manpower
3. Drawings
Action Items
1. Need Mat, Thilan, and Scott to sit down and review all of the remaining work and come up with a detailed plan that will allow us to track the project closer.
2. Crew progress must be checked daily by the fab shop supervisor and project engineer against the expectations and adjustments made immediately. The group leader will also start making spot checks on the job using the schedule as a map.
3. We will implement longer shifts or two shifts everywhere possible.