(Created page with "This was the first CTF upgrade meeting. The following items were discussed and some action items were generated: * 1. The bodies of the two 12" Kinney pump inlet isolation va...")
 
 
(One intermediate revision by the same user not shown)
Line 1: Line 1:
This was the first CTF upgrade meeting. The following items were discussed and some action items were generated:
+
Attenders: Mat Wright, Thilan Wijeration, Alicia Saringer, Sasa Radovic, Shirley Yang
  
* 1. The bodies of the two 12" Kinney pump inlet isolation valves are rusty. They were from the trailer. Two new Flowseal high performance butterfly valves with soft seat will
+
The following items were updated during this meeting
be pursued when relocating the Kinney pumps. By doing it, downtime of the kinney pump 1 is minimized when relocating the kinney pump 2. The new valve is about $20,000/each.
+
 
* 2. Thilan is going to perform a pressure drop calculation of the kinney pump discharge section to see if 2" header will be big enough.  
+
* 1. Four vendors were contacted for the overhaul of the Kinney pump system.  
* 3. Sasa / Jonathan confirmed that there would be no need for downtime of the control system for relocating the kinney pumps.  
+
      * I)Tencarva provided a repair estimate of $49134 / unit for the blower and $19824 / uint for the liquid ring pump.  
* 4. Jonathan suggested replacing necessary EVs to PVs since EVs are much more expensive and require heavy maintenance.
+
      * II) Universal Air & Gas products Corporation provided part cost for rebuilding a blower, which is $16724. They ask $850 for evaluation and will provide the labor cost based on the evaluation result. They  can't rebuid the liquid ring pump
* 5. Mat and Shirley will figure out all tie-ins for the recovery compressor system and gas management system and estimate the required downtime.
+
      * III)JJ Crewe asked for $2760/unit for evaluation of the blower before quoting the rebuild price.  
* 6. Once the fund is available, Alicia is going to order material for building two recovery compressors.
+
      * IV) A field engineer from Gasho visited our system but we haven't heard anything back from them at this point. A follow-up email has been sent to Jennifer Gasho.
 +
* 2. Alicia brought her concern about the rebuiding of the Kinney pump system. She wondered how long the manufacture would be able to support these models since they are very old.  
 +
* 3. Sasa is going to check if the motors on Kinney pump systems need an overhaul.
 +
* 4. All tie-ins for new gas management skid have been identified and documented. We'd like to have all tie-ins to be done during the CTF shut down for CB3 to short future shut-down time.

Latest revision as of 13:01, 4 November 2016

Attenders: Mat Wright, Thilan Wijeration, Alicia Saringer, Sasa Radovic, Shirley Yang

The following items were updated during this meeting

  • 1. Four vendors were contacted for the overhaul of the Kinney pump system.
      * I)Tencarva provided a repair estimate of $49134 / unit for the blower and $19824 / uint for the liquid ring pump. 
      * II) Universal Air & Gas products Corporation provided part cost for rebuilding a blower, which is $16724. They ask $850 for evaluation and will provide the labor cost based on the evaluation result. They  can't rebuid the liquid ring pump
      * III)JJ Crewe asked for $2760/unit for evaluation of the blower before quoting the rebuild price. 
      * IV) A field engineer from Gasho visited our system but we haven't heard anything back from them at this point. A follow-up email has been sent to Jennifer Gasho.
  • 2. Alicia brought her concern about the rebuiding of the Kinney pump system. She wondered how long the manufacture would be able to support these models since they are very old.
  • 3. Sasa is going to check if the motors on Kinney pump systems need an overhaul.
  • 4. All tie-ins for new gas management skid have been identified and documented. We'd like to have all tie-ins to be done during the CTF shut down for CB3 to short future shut-down time.