<strong>ESR & Hall Coordination Meetings </strong>
  
== Attendance ==
+
* [[ ESR Halls | ESR Halls - Cryogenics Coordination Meetings ]]
 
 
Creel, Wright, Schleeper, Hasan, Oren, Gomez, Kepple, Meekins, Kashy, Brindza
 
 
 
== Agenda and Notes ==
 
 
 
'''1. ESR Capacity'''
 
 
 
ESR is a variable capacity machine producing 4.5K and 15K temperatures.
 
 
 
The two endpoints of capacity are approximately (1,500W at 4.5K and 0W 15K) or (800W at 4.5K and 1,200W at 15K).
 
 
 
The addition of the CHL-ESR transferline adds up to 20 g/s at 4.5K with increased electrical power and LN2 costs at CHL.
 
 
 
 
 
'''2. ESR Reliability '''
 
 
 
Operating ESR at higher capacities will effect availability.
 
 
 
 
 
'''3. FY17 12GeV Needs '''
 
 
 
''Hall C''
 
 
 
Q2 cooldown October 16'
 
 
 
Dipole cooldown in February 16'
 
 
 
Q3 cooldown December 16'
 
 
 
''Hall B''
 
 
 
Torus stays online
 
 
 
Solenoid cooldown May-July 17'
 
 
 
 
 
'''4. Hall Non-12GeV Needs '''
 
 
 
 
 
'''5. Cryo Needs '''
 
 
 
Cryo needs to know the prioritized order of how the loads are to be brought back online following problems at the ESR. 
 
 
 
 
 
The Hall's need to warm up (or not cool) any loads not required for the Physics program. This will reduce the strain on ESR, it will increase availability, it will increase the capacity availble to recover loads after any ESR problems, and it will reduce power and LN2 costs.
 
 
 
== Action Items ==
 
 
 
Attendees will notify cryo of any changes to the plan and future meetings will be held as required.
 