Difference between revisions of "Nusair Hasan work items"
From Cryowiki
Jump to navigationJump to search (→OPS) |
(→OPS) |
||
(One intermediate revision by the same user not shown) | |||
Line 49: | Line 49: | ||
Updated 1/30/2017 | Updated 1/30/2017 | ||
+ | |||
+ | * CHL General | ||
+ | |||
+ | - Recovery C9 Load Valve Troubleshoot (do not unload on request) | ||
+ | - Purifier Regen. (issues with heating properly). | ||
+ | |||
* CHL1 / SC1 / SL-FEL | * CHL1 / SC1 / SL-FEL | ||
Line 55: | Line 61: | ||
- on that note, we need to schedule a test (possibly at the end of the run) to measure CHL1 capacity (i.e. whether it's able to supply 30 g/s 4K flow without hampering LINAC operations). | - on that note, we need to schedule a test (possibly at the end of the run) to measure CHL1 capacity (i.e. whether it's able to supply 30 g/s 4K flow without hampering LINAC operations). | ||
- Measure ESR daily helium losses (whether 'fixing' Hall C U-Tube affected the daily losses). | - Measure ESR daily helium losses (whether 'fixing' Hall C U-Tube affected the daily losses). | ||
+ | |||
* CHL2 / SC2 / NL | * CHL2 / SC2 / NL |
Latest revision as of 15:07, 30 January 2017
Projects
Updated: 1/30/2017
- LINAC Heater Control Algorithm
- Write-up Pseudo-Code based on Algorithm (sent 1/24/2017) - Develop design for UI - Troubleshoot / Find Bugs in the Algorithm
- ESR2 Process Model
- Model Development (Completed FY 2016) - Load Support Modes (Completed FY 2016) - Mode / Performance Analysis - CEC 2017 Paper
- CTF CBX3 Testing
- Model Development - Thilan (Completed FY 2016) - Testing Spreadsheet Development - Testing Modes - Analysis - Possible CEC 2017 Paper
- CHL2 C6 Commissioning
- Development of Plans - Calculation spreadsheet development - Testing and Analysis
- JLab 2KCBX Performance Analysis
- Discuss with Rao
- JLab Operational Procedures
- CHL2 4K / 2K Pump-down (Completed FY 2016) - CHL2 Warm Compressor Start-up / Swing / Switch-over
- JLab Helium Inventory Monitoring
- Model Development (Completed FY 2015) - Data Collection and Revisions (Completed FY 2016) - Upgrades - CEC 2017 Paper
OPS
Updated 1/30/2017
- CHL General
- Recovery C9 Load Valve Troubleshoot (do not unload on request) - Purifier Regen. (issues with heating properly).
- CHL1 / SC1 / SL-FEL
- CHL-ESR TL in use for Hall B C/D - on that note, we need to schedule a test (possibly at the end of the run) to measure CHL1 capacity (i.e. whether it's able to supply 30 g/s 4K flow without hampering LINAC operations). - Measure ESR daily helium losses (whether 'fixing' Hall C U-Tube affected the daily losses).
- CHL2 / SC2 / NL
- Dewar LL probe is anything but accurate! - NL Auto-heat is having issues with RF mis-match (LEM values were set: week of 1/23). - SC2 Trip - Secure Control Development (How to automatically set-up CHL2 in the event of a trip?). - iocnl1 reboot-restore issue (Fixed: week of 1/23) - superMOPS testing (Done: week of 1/23) - SC2 HX-10N Dp at 3 mbar (1/30/2017)