Difference between revisions of "Alicia Saringer work items"

From Cryowiki
Jump to navigationJump to search
 
(32 intermediate revisions by the same user not shown)
Line 1: Line 1:
Dunham-Bush Check Valve Hinge Installation Verification (Complete)
 
  
Recovery Compressor Pipe Analysis (Complete)
+
--Relief spool OSP (in review)
  
Install the C.V. on C9
+
--CHL2 Relief Valve OSP
  
LCLS II Spreader Analysis (Complete), Start White Paper (Complete), Comment Adjudication (Complete), Incorporate Comments and Develop Final Draft
+
--New Kinney Tank (Leaked sealed/$1400 repair quote from Triad-schedule with Shirley)
  
Relief Valve Instrumentation/Protected Zones (CTF Complete)
+
--EV development (drawing in process, most parts ordered)
  
-Schedule service of two to six relief valves during shutdown. Plan for addressing all relief valves developed, RV2081, RV2420, RV2440 Ready for this shutdown, Address the relief valves on the Bayonet Cans.
+
--CTF Inventory Calculation Refinement
  
-Continue to the other plants.  
+
--P&I for Nate on removing and installing the junction box relief valves
 +
 +
--Drawings for review LL sensor, relief valve set drawings, compressor relief valve dwg. (Complete)
 +
  -Order forms
 +
  -OSP
  
Liquid Level Indicator determined to go on the coalescer. Develop a drawing and plan.
+
--CHL2 RVs
  
CHL Recovery Compressor Header Redesign
+
--CTF Dewar and Main Compressor Relief Valves.
  
CTF Warm-Up/Cool Down (Complete-Review Thilan's plan)-Complete
+
--Working on changing the next three relief valves, RV2450, RV243SU and RV243RT. 
  
Kinney Water Line Leak-Complete
+
--Kinney Water Line Leak-Will be addressed during relocation. By-pass line leakage
  
Relief Valves to Replace at CTF (Complete)
+
--CTF Recovery Compressor C4 and C6 P&I
  
Sight Glass Assembly Installation at Kinney Pump - ETA 2/7/2017
+
--Install the C.V. on C9
  
CTF Recovery Compressor C4 and C6 P&I
+
--Pressure Systems Part 9 review and comments to K. Dixon -Done
 +
--Flexitallic Flange torque requirements -Done
  
Develop CTF Document - Ongoing
+
--Develop Milestone/schedule -Done
  
CTF Spreadsheets - Ongoing
+
-Someone to cut Kinney Sight glass.  -Done
 +
 
 +
--FlowSafe Dwgs per selected based on calculation. -Done
 +
 
 +
--Sightglass for the RV on compressors -Done
 +
 +
 
 +
--KelF ring for EV245RT/DWG Dimensions.  -Done
 +
 
 +
--Addressing EV245RT Leak. Currently working on repair.  -Done 
 +
 
 +
 
 +
 
 +
--Sight Glass Assembly Installation at Kinney Pump -  -Done 
 +
 
 +
 
 +
--Relief Valve Instrumentation/Protected Zones (CTF Complete)
 +
 
 +
 
 +
--Id. all RV Category on spreadsheet completed. Proceed to inspect then in accordance with the IC and get all ASME relief valves in the plant.
 +
 
 +
--Id relief valves on CHL2
 +
 
 +
--Liquid Level Indicator determined to go on the coalescer. Develop a drawing and plan.
 +
Waiting for the drawings to be completed. The John C Ernst soft parts are on order. 
 +
 
 +
--CHL Recovery Compressor Header Redesign
 +
 +
--Develop CTF Document - Ongoing
 +
 
 +
--CTF Spreadsheets - Ongoing - Get with Bill about full startup after power outage
 +
 
 +
--CTF Warm-Up/Cool Down (Complete-Review Thilan's plan)-Complete
 +
 
 +
  --Recovery Compressor LOTO Review (Complete)-Second Review Complete
 +
 
 +
--Dunham-Bush Check Valve Hinge Installation Verification (Complete)
 +
 
 +
--Recovery Compressor Pipe Analysis (Complete)
 +
--LCLS II Spreader Analysis (Complete), Start White Paper (Complete), Comment Adjudication (Complete), Incorporate Comments and Develop Final Draft(Complete)-Revise to incorporate different lifting mechanisms --(Complete)
 +
--Bolting "Procedure" - complete
 +
--Shaft Seal on Kinney for M. Wright - complete

Latest revision as of 12:51, 17 May 2017

--Relief spool OSP (in review)
--CHL2 Relief Valve OSP
--New Kinney Tank (Leaked sealed/$1400 repair quote from Triad-schedule with Shirley)
--EV development (drawing in process, most parts ordered)
--CTF Inventory Calculation Refinement
--P&I for Nate on removing and installing the junction box relief valves

--Drawings for review LL sensor, relief valve set drawings, compressor relief valve dwg. (Complete)
  -Order forms
  -OSP
--CHL2 RVs
--CTF Dewar and Main Compressor Relief Valves. 
--Working on changing the next three relief valves, RV2450, RV243SU and RV243RT.  
--Kinney Water Line Leak-Will be addressed during relocation. By-pass line leakage
--CTF Recovery Compressor C4 and C6 P&I 
--Install the C.V. on C9
--Pressure Systems Part 9 review and comments to K. Dixon -Done
--Flexitallic Flange torque requirements -Done
--Develop Milestone/schedule -Done
-Someone to cut Kinney Sight glass.  -Done
--FlowSafe Dwgs per selected based on calculation. -Done
--Sightglass for the RV on compressors -Done

--KelF ring for EV245RT/DWG Dimensions.  -Done
--Addressing EV245RT Leak. Currently working on repair.  -Done  


--Sight Glass Assembly Installation at Kinney Pump -  -Done  


--Relief Valve Instrumentation/Protected Zones (CTF Complete)


--Id. all RV Category on spreadsheet completed. Proceed to inspect then in accordance with the IC and get all ASME relief valves in the plant.

--Id relief valves on CHL2 
--Liquid Level Indicator determined to go on the coalescer. Develop a drawing and plan.
Waiting for the drawings to be completed. The John C Ernst soft parts are on order.  
--CHL Recovery Compressor Header Redesign

--Develop CTF Document - Ongoing
--CTF Spreadsheets - Ongoing - Get with Bill about full startup after power outage
--CTF Warm-Up/Cool Down (Complete-Review Thilan's plan)-Complete
 --Recovery Compressor LOTO Review (Complete)-Second Review Complete
--Dunham-Bush Check Valve Hinge Installation Verification (Complete)
--Recovery Compressor Pipe Analysis (Complete)
--LCLS II Spreader Analysis (Complete), Start White Paper (Complete), Comment Adjudication (Complete), Incorporate Comments and Develop Final Draft(Complete)-Revise to incorporate different lifting mechanisms --(Complete)
--Bolting "Procedure" - complete
--Shaft Seal on Kinney for M. Wright - complete