--Pressure Systems Part 9 review and comments to K. Dixon
 
--Flexitallic Flange torque requirements
 
  
  --Develop Milestone/schedule -Done
+
  --Relief spool OSP (in review)
 +
 
 +
--CHL2 Relief Valve OSP
  
  --EV development
+
  --New Kinney Tank (Leaked sealed/$1400 repair quote from Triad-schedule with Shirley)
  
  -Someone to cut Kinney Sight glass.  -Done
+
  --EV development (drawing in process, most parts ordered)
  
  --FlowSafe Dwgs per selected based on calculation. -Done
+
  --CTF Inventory Calculation Refinement
  
  --Sightglass for the RV on compressors -Done
+
  --P&I for Nate on removing and installing the junction box relief valves
 
   
 
   
 +
--Drawings for review LL sensor, relief valve set drawings, compressor relief valve dwg. (Complete)
 +
  -Order forms
 +
  -OSP
  
  --KelF ring for EV245RT/DWG Dimensions.  -Done
+
  --CHL2 RVs
  
 
  --CTF Dewar and Main Compressor Relief Valves.  
 
  --CTF Dewar and Main Compressor Relief Valves.  
  
  --Looking into reducing/mitigating cavitation in the Kinney Pump system to try and bring down the suction line pressure.  
+
  --Working on changing the next three relief valves, RV2450, RV243SU and RV243RT. 
 +
 
 +
--Kinney Water Line Leak-Will be addressed during relocation. By-pass line leakage
 +
 
 +
--CTF Recovery Compressor C4 and C6 P&I
 +
 
 +
--Install the C.V. on C9
 +
 
 +
--Pressure Systems Part 9 review and comments to K. Dixon -Done
 +
--Flexitallic Flange torque requirements -Done
  
  -Working on changing the next three relief valves, RV2450, RV243SU and RV243RT. 
+
  --Develop Milestone/schedule -Done
  
  --Addressing EV245RT Leak. Currently working on repair.  -Done
+
  -Someone to cut Kinney Sight glass.  -Done
  
  --Add documents to docushare and recreate PS-7 for C9 Header
+
  --FlowSafe Dwgs per selected based on calculation. -Done
  
  --Sight Glass Assembly Installation at Kinney Pump - Received needs to be cut.
+
  --Sightglass for the RV on compressors -Done
 +
  
 +
--KelF ring for EV245RT/DWG Dimensions.  -Done
  
  --Kinney Water Line Leak-Will be addressed during relocation. By-pass line leakage
+
  --Addressing EV245RT Leak. Currently working on repair.  -Done 
  
--CTF Recovery Compressor C4 and C6 P&I
 
  
--Install the C.V. on C9
 
  
 +
--Sight Glass Assembly Installation at Kinney Pump -  -Done 
  
  
Line 60: Line 73:
 
  --Recovery Compressor Pipe Analysis (Complete)
 
  --Recovery Compressor Pipe Analysis (Complete)
 
  --LCLS II Spreader Analysis (Complete), Start White Paper (Complete), Comment Adjudication (Complete), Incorporate Comments and Develop Final Draft(Complete)-Revise to incorporate different lifting mechanisms --(Complete)
 
  --LCLS II Spreader Analysis (Complete), Start White Paper (Complete), Comment Adjudication (Complete), Incorporate Comments and Develop Final Draft(Complete)-Revise to incorporate different lifting mechanisms --(Complete)
 +
--Bolting "Procedure" - complete
 +
--Shaft Seal on Kinney for M. Wright - complete

Latest revision as of 11:51, 17 May 2017

--Relief spool OSP (in review)
--CHL2 Relief Valve OSP
--New Kinney Tank (Leaked sealed/$1400 repair quote from Triad-schedule with Shirley)
--EV development (drawing in process, most parts ordered)
--CTF Inventory Calculation Refinement
--P&I for Nate on removing and installing the junction box relief valves

--Drawings for review LL sensor, relief valve set drawings, compressor relief valve dwg. (Complete)
  -Order forms
  -OSP
--CHL2 RVs
--CTF Dewar and Main Compressor Relief Valves. 
--Working on changing the next three relief valves, RV2450, RV243SU and RV243RT.  
--Kinney Water Line Leak-Will be addressed during relocation. By-pass line leakage
--CTF Recovery Compressor C4 and C6 P&I 
--Install the C.V. on C9
--Pressure Systems Part 9 review and comments to K. Dixon -Done
--Flexitallic Flange torque requirements -Done
--Develop Milestone/schedule -Done
-Someone to cut Kinney Sight glass.  -Done
--FlowSafe Dwgs per selected based on calculation. -Done
--Sightglass for the RV on compressors -Done

--KelF ring for EV245RT/DWG Dimensions.  -Done
--Addressing EV245RT Leak. Currently working on repair.  -Done  


--Sight Glass Assembly Installation at Kinney Pump -  -Done  


--Relief Valve Instrumentation/Protected Zones (CTF Complete)


--Id. all RV Category on spreadsheet completed. Proceed to inspect then in accordance with the IC and get all ASME relief valves in the plant.

--Id relief valves on CHL2 
--Liquid Level Indicator determined to go on the coalescer. Develop a drawing and plan.
Waiting for the drawings to be completed. The John C Ernst soft parts are on order.  
--CHL Recovery Compressor Header Redesign

--Develop CTF Document - Ongoing
--CTF Spreadsheets - Ongoing - Get with Bill about full startup after power outage
--CTF Warm-Up/Cool Down (Complete-Review Thilan's plan)-Complete
 --Recovery Compressor LOTO Review (Complete)-Second Review Complete
--Dunham-Bush Check Valve Hinge Installation Verification (Complete)
--Recovery Compressor Pipe Analysis (Complete)
--LCLS II Spreader Analysis (Complete), Start White Paper (Complete), Comment Adjudication (Complete), Incorporate Comments and Develop Final Draft(Complete)-Revise to incorporate different lifting mechanisms --(Complete)
--Bolting "Procedure" - complete
--Shaft Seal on Kinney for M. Wright - complete