Difference between revisions of "11/10/2016 Meeting"
(Created page with " == Attendance == Thompson, Creel, Dixon, Oren, Michalski Wright doing utubes == Agenda and Notes == '''1. Operations ''' LINAC Magnet power supply repaired. A warm wi...") |
|||
Line 22: | Line 22: | ||
CHL1 | CHL1 | ||
− | + | Old recovery C8 was removed and new C7 was installed yesterday. Piping and electrical work is expected to take about another week. | |
+ | |||
CHL2 | CHL2 | ||
Line 31: | Line 32: | ||
ESR | ESR | ||
− | + | Hall C SHMS Q2 utubes installed yesterday. Cooldown will start today. | |
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
CTF | CTF | ||
− | + | Plant operating normally. | |
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
HDR | HDR | ||
− | + | Plant operating normally. | |
Line 83: | Line 50: | ||
UITF | UITF | ||
− | + | Warm return VJ line section above cryomodule should be installed by COB Friday. Vacuum pump tie in was completed last week. | |
− | + | ||
MSU | MSU | ||
− | + | 2K Cold Box design work shifted over to Michael. Contractor on site installing cold box tie ins and platforms. | |
LCLS2 | LCLS2 | ||
− | + | Installation work for the cryo plant was officially moved to the SLAC team. The team is currently evaluating the bids on some of the utility support equipment. Bayonets etc. are complete and we are going to ship them to PHPK as soon as possible. Dana will advise when paperwork is done. The recovery compressor parts purchasing is underway. Work has begun on the frames. | |
− | |||
'''3. Manpower ''' | '''3. Manpower ''' | ||
− | The new EE regular employee and ECAD contract employee | + | The new EE regular employee and ECAD contract employee started on Nov 1. |
− | We | + | We had an interview with Dr. Wang. |
Revision as of 10:08, 10 November 2016
Attendance
Thompson, Creel, Dixon, Oren, Michalski
Wright doing utubes
Agenda and Notes
1. Operations
LINAC
Magnet power supply repaired.
A warm window on 2L06 failed and required utubes to support repairs. 2L07 also ingested air into the beam line and now requires cryo cycling
The test plan to raise pressure in the linac failed on the first step and pressure was again lowered.
CHL1
Old recovery C8 was removed and new C7 was installed yesterday. Piping and electrical work is expected to take about another week.
CHL2
Normal
ESR
Hall C SHMS Q2 utubes installed yesterday. Cooldown will start today.
CTF
Plant operating normally.
HDR
Plant operating normally.
2. Projects
UITF
Warm return VJ line section above cryomodule should be installed by COB Friday. Vacuum pump tie in was completed last week.
MSU
2K Cold Box design work shifted over to Michael. Contractor on site installing cold box tie ins and platforms.
LCLS2
Installation work for the cryo plant was officially moved to the SLAC team. The team is currently evaluating the bids on some of the utility support equipment. Bayonets etc. are complete and we are going to ship them to PHPK as soon as possible. Dana will advise when paperwork is done. The recovery compressor parts purchasing is underway. Work has begun on the frames.
3. Manpower
The new EE regular employee and ECAD contract employee started on Nov 1.
We had an interview with Dr. Wang.
4. Info from Will
1. Appraisals and new expectations 2. Watch all spending on OPS and ENG accounts
4. Other
Gave STEM talks with LN2 demonstrations to three high school science classes this week.
Action Items
1. Must keep meeting to no more than 30 minutes