Difference between revisions of "Nate Laverdure work items"
From Cryowiki
Jump to navigationJump to searchLine 10: | Line 10: | ||
==SLAC LCLS-II== | ==SLAC LCLS-II== | ||
− | Prepare 2k cold box design materials for February 2017 FDR | + | [[SLAC LCLS-II 2K Cold Box | SLAC LCLS-II 2K Cold Box]] |
+ | * Prepare 2k cold box design materials for February 2017 FDR | ||
==JLab== | ==JLab== |
Revision as of 12:24, 19 January 2017
MSU FRIB
Organize and publish pressure system documentation for main compressor system
- Update flexibility analysis of large main helium piping in cold box room and compressor room; perform calculations for hangers and supports
- Review and correct errors in relief valve calc sheets
Review 3 atm helium model in cold box room
- Create u-tube purge plan in cold box room
Review LS2 cooldown transfer line segment
SLAC LCLS-II
- Prepare 2k cold box design materials for February 2017 FDR
JLab
Organize cryo pressure systems
- to supersede existing cryo pressure systems work package filing system
- to provide a place for filing recurring inspections of systems and equipment
- to provide a place for documenting future repairs/alterations
- to integrate with the pressure systems work being done by other groups