Difference between revisions of "Alicia Saringer work items"
From Cryowiki
Jump to navigationJump to searchLine 1: | Line 1: | ||
− | Dunham-Bush Check Valve Hinge Installation Verification | + | Dunham-Bush Check Valve Hinge Installation Verification (Complete) |
Recovery Compressor Pipe Analysis | Recovery Compressor Pipe Analysis | ||
Line 5: | Line 5: | ||
Install the C.V. on C9 | Install the C.V. on C9 | ||
− | LCLS II Spreader Analysis (Complete) | + | LCLS II Spreader Analysis (Complete), Start White Paper |
Relief Valve Instrumentation/Protected Zones | Relief Valve Instrumentation/Protected Zones | ||
Line 19: | Line 19: | ||
Relief Valves to Replace at CTF | Relief Valves to Replace at CTF | ||
− | Sight Glass Assembly Installation at Kinney Pump | + | Sight Glass Assembly Installation at Kinney Pump - ETA 2/2/2017 |
Revision as of 16:05, 26 January 2017
Dunham-Bush Check Valve Hinge Installation Verification (Complete)
Recovery Compressor Pipe Analysis
Install the C.V. on C9
LCLS II Spreader Analysis (Complete), Start White Paper
Relief Valve Instrumentation/Protected Zones
Liquid Level Indicator
CHL Recovery Compressor Header Redesign
CTF Warm-Up/Cool Down
Kinney Water Line Leak
Relief Valves to Replace at CTF
Sight Glass Assembly Installation at Kinney Pump - ETA 2/2/2017