Difference between revisions of "Alicia Saringer work items"

From Cryowiki
Jump to navigationJump to search
Line 7: Line 7:
 
LCLS II Spreader Analysis (Complete), Start White Paper (Complete)
 
LCLS II Spreader Analysis (Complete), Start White Paper (Complete)
  
Relief Valve Instrumentation/Protected Zones
+
Relief Valve Instrumentation/Protected Zones (CTF Complete)
 +
 
 +
-Schedule service of two relief valves during shutdown.
 +
-Continue to the other plants.
  
 
Liquid Level Indicator
 
Liquid Level Indicator

Revision as of 17:21, 31 January 2017

Dunham-Bush Check Valve Hinge Installation Verification (Complete)

Recovery Compressor Pipe Analysis

Install the C.V. on C9

LCLS II Spreader Analysis (Complete), Start White Paper (Complete)

Relief Valve Instrumentation/Protected Zones (CTF Complete)

-Schedule service of two relief valves during shutdown. -Continue to the other plants.

Liquid Level Indicator

CHL Recovery Compressor Header Redesign

CTF Warm-Up/Cool Down (Complete-Review Thilan's plan)

Kinney Water Line Leak

Relief Valves to Replace at CTF (Complete)

Sight Glass Assembly Installation at Kinney Pump - ETA 2/2/2017

Develop CTF Document - Ongoing

CTF Spreadsheets - Ongoing