Dunham-Bush Check Valve Hinge Installation Verification (Complete)
+
Sight Glass Assembly Installation at Kinney Pump - Received needs to be cut.
  
Recovery Compressor Pipe Analysis (Complete)
+
Addressing EV245RT Leak.
  
 
Install the C.V. on C9
 
Install the C.V. on C9
Line 22: Line 22:
  
 
Relief Valves to Replace at CTF (Complete)
 
Relief Valves to Replace at CTF (Complete)
 
Sight Glass Assembly Installation at Kinney Pump - ETA 2/7/2017
 
  
 
CTF Recovery Compressor C4 and C6 P&I  
 
CTF Recovery Compressor C4 and C6 P&I  
Line 30: Line 28:
  
 
CTF Spreadsheets - Ongoing - Get with Bill about full startup after power outage
 
CTF Spreadsheets - Ongoing - Get with Bill about full startup after power outage
 +
 +
Dunham-Bush Check Valve Hinge Installation Verification (Complete)
 +
 +
Recovery Compressor Pipe Analysis (Complete)

Revision as of 12:22, 17 February 2017

Sight Glass Assembly Installation at Kinney Pump - Received needs to be cut.

Addressing EV245RT Leak.

Install the C.V. on C9

LCLS II Spreader Analysis (Complete), Start White Paper (Complete), Comment Adjudication (Complete), Incorporate Comments and Develop Final Draft(Complete)

Relief Valve Instrumentation/Protected Zones (CTF Complete)

-Schedule service of two to six relief valves during shutdown. Plan for addressing all relief valves developed, RV2081, RV2420, RV2440 Ready for this shutdown, Address the relief valves on the Bayonet Cans.

-Continue to the other plants.

Liquid Level Indicator determined to go on the coalescer. Develop a drawing and plan.

CHL Recovery Compressor Header Redesign

CTF Warm-Up/Cool Down (Complete-Review Thilan's plan)-Complete

Kinney Water Line Leak-Complete

Relief Valves to Replace at CTF (Complete)

CTF Recovery Compressor C4 and C6 P&I

Develop CTF Document - Ongoing

CTF Spreadsheets - Ongoing - Get with Bill about full startup after power outage

Dunham-Bush Check Valve Hinge Installation Verification (Complete)

Recovery Compressor Pipe Analysis (Complete)