#CHL-ESR x-fer line will be in use occasionally over the next week.
 
#CHL-ESR x-fer line will be in use occasionally over the next week.
 
#T2 will need to be stopped to facilitate simple trouble shooting on inlet valve/actuator.
 
#T2 will need to be stopped to facilitate simple trouble shooting on inlet valve/actuator.
 
==MSU FRIB==
 
Organize and publish pressure system documentation for pressure systems.  Actions are as listed in the summary document.
 
 
#IA complete
 
#GV complete
 
#LND complete
 
#waiting for examination docs from embler.
 

Revision as of 09:46, 16 February 2017

JLab

2/16 Update Organize cryo pressure systems

  • CHL:
  1 Replacement/upgrade of LN2 fill station gauging:
    -Materials: On-site
    -Pressure System:  Standard Maintenance
    -Drawings: N/A
    -Fabrication:  N/A
    -Operations:  Assigned Tank 2 complete.  Tank 1 is being prioritized.
    -Testing:  Snoop upon installation.
  2 CHL Guard Vacuum
    -Materials:  installed
    -Pressure System:  Signed
    -Drawings: Complete
    -Fabrication: N/A
    -Operations: Will test run upon completion of electrical and IA installation.
    -Testing:  To be initial service leak checked upon completion of electrical work.  Pump temperatures will also need to be monitored.
  3 LN2 Dewar #1 instrumentation tubing replacement
    -Materials:  On-site
    -Pressure System:  Signed
    -Drawings: Complete
    -Fabrication: All paperwork and materials are with Scott.  He is scheduling.
    -Operations: N/A
    -Testing:  To be initial service leak checked upon completion.  


  4 LN2 PBC leaks
    -Materials:  TBD
    -Pressure System:  TBD
    -Drawings: TBD
    -Fabrication: TBD
    -Operations: All leaks have been identified and tabulated.  Ops is investigating the repair of threaded connections.
    -Testing:  Snoop


  5 CHL Recovery Purifier Sieve replacement
    -Materials:  on-site
    -Pressure System:  N/A
    -Drawings: N/A
    -Fabrication: N/A
    -Operations: P5 sieve replaced and ready for use.
    -Testing:  N/A


  6 ESR ORS Carbon Replacement
    -Materials:  Lifting adapter approved by Sprouse.  Estimating ~$350 for materials
    -Pressure System:  N/A
    -Drawings: Need to be developed.
    -Fabrication: awaiting drawings
    -Operations: Needs to be scheduled/planned.  Probably next summer
    -Testing:  Spool pieces will need to be tested.
  7 ESR 15K U-tube
    -Materials:  ordered
    -Pressure System:  signed
    -Drawings: issued.
    -Fabrication: in fabrication (expect to test by 3/3/17)
    -Operations: U-tube will be stabbed at earliest convenience (when it will not impact target schedule)
    -Testing:  pressure test per DPF
  8 ESR Oil collection
    -Materials:  TBD
    -Pressure System:  TBD
    -Drawings: TBD
    -Fabrication: TBD
    -Operations: May require piping removal or plant shutdown
    -Testing:  not likely. category D piping at most.


  9 CHL IA modification
    -Materials:  ordered
    -Pressure System:  TBD
    -Drawings: in development
    -Fabrication: TBD
    -Operations: N/A
    -Testing:  Initial service leak test
  10 CHL purifier sieve heater
    -Materials:  Awaiting design
    -Pressure System:  Awaiting design
    -Drawings:  Awaiting basic design
    -Fabrication:  Awaiting drawings
    -Operations:  TBD
    -Testing: Test per B31.3, with consideration for temperature requirements.

ESR Status

  1. Halls A, B, and C are on cold return. Hall C magnets filling.
  2. Hall C is cooling SHMS Dipole to 100K. U-tubes were stabbed Tuesday.
  3. Hall C target system is being cleaned. Not connected to ESR or recovery as of now.
  4. CHL-ESR x-fer line will be in use occasionally over the next week.
  5. T2 will need to be stopped to facilitate simple trouble shooting on inlet valve/actuator.