Difference between revisions of "Alicia Saringer work items"

From Cryowiki
Jump to navigationJump to search
Line 5: Line 5:
 
  --Addressing EV245RT Leak. Currently working on identifying exact repair kit information.  
 
  --Addressing EV245RT Leak. Currently working on identifying exact repair kit information.  
  
  Install the C.V. on C9
+
  --Kinney Water Line Leak-Will be addressed during relocation. By-pass line leakage
 +
 
 +
--CTF Recovery Compressor C4 and C6 P&I
 +
 
 +
 
 +
--Install the C.V. on C9
  
 
  --LCLS II Spreader Analysis (Complete), Start White Paper (Complete), Comment Adjudication (Complete), Incorporate Comments and Develop Final Draft(Complete)-Revise to incorporate different lifting mechanisms
 
  --LCLS II Spreader Analysis (Complete), Start White Paper (Complete), Comment Adjudication (Complete), Incorporate Comments and Develop Final Draft(Complete)-Revise to incorporate different lifting mechanisms
Line 26: Line 31:
 
  CTF Warm-Up/Cool Down (Complete-Review Thilan's plan)-Complete
 
  CTF Warm-Up/Cool Down (Complete-Review Thilan's plan)-Complete
  
Kinney Water Line Leak-Will be addressed during relocation. By-pass line leakage
+
  --Recovery Compressor LOTO Review (Complete)-Second Review Complete
 
 
--CTF Recovery Compressor C4 and C6 P&I
 
 
 
--Recovery Compressor LOTO Review (Complete)-Second Review Complete
 
  
 
  --Develop CTF Document - Ongoing
 
  --Develop CTF Document - Ongoing

Revision as of 15:51, 1 March 2017

--Add documents to docushare and recreate PS-7 for C9 Header 
--Sight Glass Assembly Installation at Kinney Pump - Received needs to be cut. 
--Addressing EV245RT Leak. Currently working on identifying exact repair kit information. 
--Kinney Water Line Leak-Will be addressed during relocation. By-pass line leakage
--CTF Recovery Compressor C4 and C6 P&I 


--Install the C.V. on C9
--LCLS II Spreader Analysis (Complete), Start White Paper (Complete), Comment Adjudication (Complete), Incorporate Comments and Develop Final Draft(Complete)-Revise to incorporate different lifting mechanisms
--Relief Valve Instrumentation/Protected Zones (CTF Complete)

-Schedule service of two to six relief valves during shutdown. Plan for addressing all relief valves developed, RV2081, RV2420, RV2440 Ready for this shutdown, Address the relief valves on the Bayonet Cans. --Pressure test the spools. (complete) --Install

--Id. all RV Category on spreadsheet.

-Id relief valves on CHL2 
--Liquid Level Indicator determined to go on the coalescer. Develop a drawing and plan.
Planned modified to go on the coalescer and the BOS.  
--CHL Recovery Compressor Header Redesign
CTF Warm-Up/Cool Down (Complete-Review Thilan's plan)-Complete
 --Recovery Compressor LOTO Review (Complete)-Second Review Complete
--Develop CTF Document - Ongoing
--CTF Spreadsheets - Ongoing - Get with Bill about full startup after power outage
--Dunham-Bush Check Valve Hinge Installation Verification (Complete)
--Recovery Compressor Pipe Analysis (Complete)