Jump to navigationJump to searchLine 8: | Line 8: | ||
--CTF Recovery Compressor C4 and C6 P&I | --CTF Recovery Compressor C4 and C6 P&I | ||
− | |||
--Install the C.V. on C9 | --Install the C.V. on C9 | ||
Line 15: | Line 14: | ||
--Relief Valve Instrumentation/Protected Zones (CTF Complete) | --Relief Valve Instrumentation/Protected Zones (CTF Complete) | ||
− | |||
-Schedule service of two to six relief valves during shutdown. Plan for addressing all relief valves developed, RV2081, RV2420, RV2440 Ready for this shutdown, Address the relief valves on the Bayonet Cans. | -Schedule service of two to six relief valves during shutdown. Plan for addressing all relief valves developed, RV2081, RV2420, RV2440 Ready for this shutdown, Address the relief valves on the Bayonet Cans. | ||
--Pressure test the spools. (complete) | --Pressure test the spools. (complete) | ||
Line 25: | Line 23: | ||
--Liquid Level Indicator determined to go on the coalescer. Develop a drawing and plan. | --Liquid Level Indicator determined to go on the coalescer. Develop a drawing and plan. | ||
− | + | Order four (4) liquid level indicators and Corey will assign someone for the drawings. The John C Ernst Valves will be serviced during the down. | |
--CHL Recovery Compressor Header Redesign | --CHL Recovery Compressor Header Redesign | ||
+ | |||
+ | --Develop CTF Document - Ongoing | ||
− | CTF Warm-Up/Cool Down (Complete-Review Thilan's plan)-Complete | + | --CTF Spreadsheets - Ongoing - Get with Bill about full startup after power outage |
+ | |||
+ | --CTF Warm-Up/Cool Down (Complete-Review Thilan's plan)-Complete | ||
--Recovery Compressor LOTO Review (Complete)-Second Review Complete | --Recovery Compressor LOTO Review (Complete)-Second Review Complete | ||
− | |||
− | |||
− | |||
− | |||
--Dunham-Bush Check Valve Hinge Installation Verification (Complete) | --Dunham-Bush Check Valve Hinge Installation Verification (Complete) | ||
--Recovery Compressor Pipe Analysis (Complete) | --Recovery Compressor Pipe Analysis (Complete) |
Revision as of 15:54, 1 March 2017
--Add documents to docushare and recreate PS-7 for C9 Header
--Sight Glass Assembly Installation at Kinney Pump - Received needs to be cut.
--Addressing EV245RT Leak. Currently working on identifying exact repair kit information.
--Kinney Water Line Leak-Will be addressed during relocation. By-pass line leakage
--CTF Recovery Compressor C4 and C6 P&I
--Install the C.V. on C9
--LCLS II Spreader Analysis (Complete), Start White Paper (Complete), Comment Adjudication (Complete), Incorporate Comments and Develop Final Draft(Complete)-Revise to incorporate different lifting mechanisms
--Relief Valve Instrumentation/Protected Zones (CTF Complete)
-Schedule service of two to six relief valves during shutdown. Plan for addressing all relief valves developed, RV2081, RV2420, RV2440 Ready for this shutdown, Address the relief valves on the Bayonet Cans. --Pressure test the spools. (complete) --Install
--Id. all RV Category on spreadsheet.
-Id relief valves on CHL2
--Liquid Level Indicator determined to go on the coalescer. Develop a drawing and plan. Order four (4) liquid level indicators and Corey will assign someone for the drawings. The John C Ernst Valves will be serviced during the down.
--CHL Recovery Compressor Header Redesign --Develop CTF Document - Ongoing
--CTF Spreadsheets - Ongoing - Get with Bill about full startup after power outage
--CTF Warm-Up/Cool Down (Complete-Review Thilan's plan)-Complete
--Recovery Compressor LOTO Review (Complete)-Second Review Complete
--Dunham-Bush Check Valve Hinge Installation Verification (Complete)
--Recovery Compressor Pipe Analysis (Complete)