Difference between revisions of "David Schleeper work items"
From Cryowiki
Jump to navigationJump to search (→JLab) |
|||
Line 64: | Line 64: | ||
#Hall A: | #Hall A: | ||
- Magnets cold, on cold return, controlling properly | - Magnets cold, on cold return, controlling properly | ||
− | - Warm flows return to | + | - Warm flows return to CHL |
− | - Target cold. | + | - Lead flows minimal |
+ | - Target cold (~300W). | ||
#Hall B:K | #Hall B:K | ||
− | - Torus at | + | - Torus at 80K |
- Warm flows return to CHL | - Warm flows return to CHL | ||
− | - Solenoid scheduled for | + | - Solenoid scheduled for August delivery |
+ | - Buffer dewar being cleaned and prepped for cool down | ||
#Hall C: | #Hall C: | ||
Line 76: | Line 78: | ||
- Warm flows return to CHL | - Warm flows return to CHL | ||
- Return transfer line replacement did not alleviate magnet pressure issue. | - Return transfer line replacement did not alleviate magnet pressure issue. | ||
− | + | - Target cold. | |
− | - Target | ||
− |
Revision as of 16:18, 15 March 2017
JLab
3/15 Update
- CHL:
1 Replacement/upgrade of LN2 fill station gauging: -Gauges have been replaced but the Dewar #1 Gauge is reading incorrectly. Working to repair.
2 CHL Guard Vacuum -Materials: installed -Pressure System: Signed -Drawings: Complete -Fabrication: Removal/repair of the hand rail. Grouting and leg re-work. -Operations: Will need to remove feet, grout, shim and anchor the feet. Will require welding. -Testing: To be initial service leak checked upon completion of electrical work. Pump temperatures will also need to be monitored.
3 LN2 Dewar #1 instrumentation tubing replacement -Materials: On-site -Pressure System: Signed -Drawings: Complete -Fabrication: All paperwork and materials are with Scott. He is scheduling. -Operations: N/A -Testing: To be initial service leak checked upon completion.
4 LN2 PBC leaks -Materials: TBD -Pressure System: TBD -Drawings: TBD -Fabrication: TBD -Operations: All leaks have been identified and tabulated. Ops is investigating the repair of threaded connections. -Testing: Snoop
5 ESR ORS Carbon Replacement -Materials: Lifting adapter approved by Sprouse. Estimating ~$350 for materials -Pressure System: N/A -Drawings: Need to be developed. Sent to Corey for him to prioritize. -Fabrication: awaiting drawings -Operations: Needs to be scheduled/planned. Probably next summer -Testing: Spool pieces will need to be tested.
6 ESR Oil collection -Materials: Ordered, waiting on sight glass to arrive. -Pressure System: N/A -Drawings: Sketch delivered to shop. -Fabrication: TBD -Operations: Will require familiarity with system prior to installation. -Testing: N/A, down stream of relief.
7 CHL IA modification -Materials: ordered -Pressure System: Cat D -Drawings: in development -Fabrication: TBD -Operations: N/A -Testing: Initial service leak test
8 NL Cool Down Tie-in -Will purge and tie-in cool down valve
ESR Status
- Hall A:
- Magnets cold, on cold return, controlling properly - Warm flows return to CHL - Lead flows minimal - Target cold (~300W).
- Hall B:K
- Torus at 80K - Warm flows return to CHL - Solenoid scheduled for August delivery - Buffer dewar being cleaned and prepped for cool down
- Hall C:
- All magnets cold, on cold return - Warm flows return to CHL - Return transfer line replacement did not alleviate magnet pressure issue. - Target cold.