Difference between revisions of "Alicia Saringer work items"
From Cryowiki
Jump to navigationJump to searchLine 1: | Line 1: | ||
− | + | --Develop Milestone/schedule | |
+ | --EV development | ||
− | -- | + | -Someone to cut Kinney Sight glass. -Done |
− | --Sightglass for the RV on compressors | + | --FlowSafe Dwgs per selected based on calculation. -Done |
+ | |||
+ | --Sightglass for the RV on compressors -Done | ||
− | --KelF ring for EV245RT/DWG Dimensions. | + | --KelF ring for EV245RT/DWG Dimensions. -Done |
+ | |||
− | |||
--CTF Dewar and Main Compressor Relief Valves. | --CTF Dewar and Main Compressor Relief Valves. | ||
Line 16: | Line 19: | ||
-Working on changing the next three relief valves, RV2450, RV243SU and RV243RT. | -Working on changing the next three relief valves, RV2450, RV243SU and RV243RT. | ||
− | --Addressing EV245RT Leak. Currently working on repair. | + | --Addressing EV245RT Leak. Currently working on repair. -Done |
− | |||
--Add documents to docushare and recreate PS-7 for C9 Header | --Add documents to docushare and recreate PS-7 for C9 Header |
Revision as of 14:08, 4 April 2017
--Develop Milestone/schedule --EV development
-Someone to cut Kinney Sight glass. -Done
--FlowSafe Dwgs per selected based on calculation. -Done
--Sightglass for the RV on compressors -Done
--KelF ring for EV245RT/DWG Dimensions. -Done
--CTF Dewar and Main Compressor Relief Valves.
--Looking into reducing/mitigating cavitation in the Kinney Pump system to try and bring down the suction line pressure.
-Working on changing the next three relief valves, RV2450, RV243SU and RV243RT.
--Addressing EV245RT Leak. Currently working on repair. -Done
--Add documents to docushare and recreate PS-7 for C9 Header
--Sight Glass Assembly Installation at Kinney Pump - Received needs to be cut.
--Kinney Water Line Leak-Will be addressed during relocation. By-pass line leakage
--CTF Recovery Compressor C4 and C6 P&I
--Install the C.V. on C9
--Relief Valve Instrumentation/Protected Zones (CTF Complete)
--Id. all RV Category on spreadsheet completed. Proceed to inspect then in accordance with the IC and get all ASME relief valves in the plant.
--Id relief valves on CHL2
--Liquid Level Indicator determined to go on the coalescer. Develop a drawing and plan. Waiting for the drawings to be completed. The John C Ernst soft parts are on order.
--CHL Recovery Compressor Header Redesign --Develop CTF Document - Ongoing
--CTF Spreadsheets - Ongoing - Get with Bill about full startup after power outage
--CTF Warm-Up/Cool Down (Complete-Review Thilan's plan)-Complete
--Recovery Compressor LOTO Review (Complete)-Second Review Complete
--Dunham-Bush Check Valve Hinge Installation Verification (Complete)
--Recovery Compressor Pipe Analysis (Complete) --LCLS II Spreader Analysis (Complete), Start White Paper (Complete), Comment Adjudication (Complete), Incorporate Comments and Develop Final Draft(Complete)-Revise to incorporate different lifting mechanisms --(Complete)