Difference between revisions of "161206"
Line 8: | Line 8: | ||
3 options for running piping outside: | 3 options for running piping outside: | ||
− | 1. Between Gas tanks and building. | + | 1. Between Gas tanks and building. Preferred because we believe that this piping route is the easiest and "cleanest" way to route the piping. Cleanest refers to being able to route the piping without having to worry about interfering with any future jobs. |
− | 2. Running the piping on top of building | + | 2. Running the piping on top of building. We believe this is a bad idea because the people will have a hard time getting around the piping. |
− | |||
− | |||
+ | 3. Running piping through the building. We believe that this route will take longer to design and fabricate. There are many more obstacles in the way that we would have to be careful to miss during the planning | ||
== How the charge Codes are used == | == How the charge Codes are used == |
Revision as of 13:42, 6 December 2016
Attendance
Mat, Shirley, Kelly, Rusty, Michele
Asked But Did Not Attend: Jonathan
Running Kinney Pump Piping outside CTF
3 options for running piping outside:
1. Between Gas tanks and building. Preferred because we believe that this piping route is the easiest and "cleanest" way to route the piping. Cleanest refers to being able to route the piping without having to worry about interfering with any future jobs.
2. Running the piping on top of building. We believe this is a bad idea because the people will have a hard time getting around the piping.
3. Running piping through the building. We believe that this route will take longer to design and fabricate. There are many more obstacles in the way that we would have to be careful to miss during the planning
How the charge Codes are used
From Email Rusty sent on Dec 2nd:
conceptual planning (FMRIGO) The effort up to a conceptual design; which is 35%
Design and materials (FMECEU) The effort from 35% design to 100% (procurement documents)
or
We would like to be able to purchase main components after the 35%.
These components are on the "Valve - List"
Review set for Dec 8, 2016
35% is done after the:
1. Process diagram is done
2. Valve is list is approved
3. Installation sequence is approved.
Most of conceptional design done to prove that job can be done with minimal effect to operations.
The estimates did not include "work already done"
Utility Tree (Pipe support) - Question from Michele during the meeting
The only piping we would expect to be on the outside pipe support is for the 12" Kinney Pump suction header.
The other piping and conduits should all be routed inside
Water piping will all be done by the cryo group.
Action Items
Rusty needs the break up between techs and designers
Send Rusty and Michele the 3 options (3D models) for Kinney piping
Need to identify the locations where the water piping is interfacing with the facilities piping.