Jump to navigationJump to search (Created page with "==JLab== Organize cryo pressure systems * CHL: # Replacement/upgrade of LN2 fill station gauging: -Materials: On-site -Pressure System: Standard Maintenance...") |
(→JLab) |
||
Line 1: | Line 1: | ||
==JLab== | ==JLab== | ||
+ | 1/25 Update | ||
Organize cryo pressure systems | Organize cryo pressure systems | ||
* CHL: | * CHL: | ||
Line 11: | Line 12: | ||
# CHL Guard Vacuum | # CHL Guard Vacuum | ||
− | -Materials: | + | -Materials: Ordered, expected on-site week of // 1/23 |
-Pressure System: Signed | -Pressure System: Signed | ||
-Drawings: Complete | -Drawings: Complete | ||
-Fabrication: N/A | -Fabrication: N/A | ||
-Operations: N/A | -Operations: N/A | ||
− | -Testing: To be initial service leak checked upon completion of electrical work. | + | -Testing: To be initial service leak checked upon completion of electrical work. Pump temperatures will also need to be monitored. |
# LN2 Dewar #1 instrumentation tubing replacement | # LN2 Dewar #1 instrumentation tubing replacement | ||
− | -Materials: | + | -Materials: Ordered |
− | -Pressure System: | + | -Pressure System: Back in DA review |
− | -Drawings: | + | -Drawings: Complete |
-Fabrication: pending material/dpf | -Fabrication: pending material/dpf | ||
-Operations: N/A | -Operations: N/A | ||
Line 41: | Line 42: | ||
-Drawings: N/A | -Drawings: N/A | ||
-Fabrication: N/A | -Fabrication: N/A | ||
− | -Operations: | + | -Operations: P5 sieve replaced and being cleaned. |
-Testing: N/A | -Testing: N/A | ||
Line 68: | Line 69: | ||
-Operations: May require piping removal or plant shutdown | -Operations: May require piping removal or plant shutdown | ||
-Testing: not likely. category D piping at most. | -Testing: not likely. category D piping at most. | ||
− | |||
==ESR Status== | ==ESR Status== |
Revision as of 08:06, 26 January 2017
JLab
1/25 Update Organize cryo pressure systems
- CHL:
# Replacement/upgrade of LN2 fill station gauging: -Materials: On-site -Pressure System: Standard Maintenance -Drawings: N/A -Fabrication: N/A -Operations: Working. Tank 2 complete. -Testing: Snoop upon installation.
# CHL Guard Vacuum -Materials: Ordered, expected on-site week of // 1/23 -Pressure System: Signed -Drawings: Complete -Fabrication: N/A -Operations: N/A -Testing: To be initial service leak checked upon completion of electrical work. Pump temperatures will also need to be monitored.
# LN2 Dewar #1 instrumentation tubing replacement -Materials: Ordered -Pressure System: Back in DA review -Drawings: Complete -Fabrication: pending material/dpf -Operations: N/A -Testing: To be initial service leak checked upon completion.
# LN2 PBC leaks -Materials: TBD -Pressure System: TBD -Drawings: TBD -Fabrication: TBD -Operations: All leaks have been identified and need to be tabulated and planned for repair/replacement. -Testing: TBD
# CHL Recovery Purifier Sieve replacement -Materials: on-site -Pressure System: N/A -Drawings: N/A -Fabrication: N/A -Operations: P5 sieve replaced and being cleaned. -Testing: N/A
# ESR ORS Carbon Replacement -Materials: Need to be identified and ordered. -Pressure System: N/A -Drawings: Need to be developed. -Fabrication: awaiting drawings -Operations: Needs to be scheduled/planned. -Testing: Snoop at joints. Spool pieces will need to be tested.
# ESR 15K U-tube -Materials: Being ordered -Pressure System: in review -Drawings: issued. -Fabrication: awaiting materials -Operations: U-tube will be stabbed at earliest convenience -Testing: pressure test per DPF
# ESR Oil collection -Materials: TBD -Pressure System: TBD -Drawings: TBD -Fabrication: TBD -Operations: May require piping removal or plant shutdown -Testing: not likely. category D piping at most.
ESR Status
-Halls A and C are cold and on cold return. -Hall C has been performing heat leak testing of the SHMS Q2. Expected to carry into week of 1/22. -Hall B is cooling solenoid. Expected to be on cold return 1/20/2017. -Hall C target system is being cleaned. Not connected to ESR or recovery as of now. -CHL-ESR x-fer line will be in use occasionally over the next week.
MSU FRIB
Organize and publish pressure system documentation for pressure systems. Actions are as listed in the summary document.