3 LN2 Dewar #1 instrumentation tubing replacement | 3 LN2 Dewar #1 instrumentation tubing replacement | ||
− | -Materials: | + | -Materials: On-site |
-Pressure System: Signed | -Pressure System: Signed | ||
-Drawings: Complete | -Drawings: Complete | ||
− | -Fabrication: | + | -Fabrication: All paperwork and materials are with Scott. He is scheduling. |
-Operations: N/A | -Operations: N/A | ||
− | -Testing: To be initial service leak checked upon completion. | + | -Testing: To be initial service leak checked upon completion. |
Line 47: | Line 47: | ||
6 ESR ORS Carbon Replacement | 6 ESR ORS Carbon Replacement | ||
− | -Materials: | + | -Materials: Lifting adapter approved by Sprouse. Estimating ~$350 for materials |
-Pressure System: N/A | -Pressure System: N/A | ||
-Drawings: Need to be developed. | -Drawings: Need to be developed. | ||
-Fabrication: awaiting drawings | -Fabrication: awaiting drawings | ||
-Operations: Needs to be scheduled/planned. | -Operations: Needs to be scheduled/planned. | ||
− | -Testing: | + | -Testing: Spool pieces will need to be tested. |
7 ESR 15K U-tube | 7 ESR 15K U-tube |
Revision as of 11:48, 15 February 2017
JLab
2/13 Update Organize cryo pressure systems
- CHL:
1 Replacement/upgrade of LN2 fill station gauging: -Materials: On-site -Pressure System: Standard Maintenance -Drawings: N/A -Fabrication: N/A -Operations: Working. Tank 2 complete. -Testing: Snoop upon installation.
2 CHL Guard Vacuum -Materials: installed -Pressure System: Signed -Drawings: Complete -Fabrication: N/A -Operations: N/A -Testing: To be initial service leak checked upon completion of electrical work. Pump temperatures will also need to be monitored.
3 LN2 Dewar #1 instrumentation tubing replacement -Materials: On-site -Pressure System: Signed -Drawings: Complete -Fabrication: All paperwork and materials are with Scott. He is scheduling. -Operations: N/A -Testing: To be initial service leak checked upon completion.
4 LN2 PBC leaks -Materials: TBD -Pressure System: TBD -Drawings: TBD -Fabrication: TBD -Operations: All leaks have been identified and tabulated. Ops is investigating the repair of threaded connections. -Testing: Snoop
5 CHL Recovery Purifier Sieve replacement -Materials: on-site -Pressure System: N/A -Drawings: N/A -Fabrication: N/A -Operations: P5 sieve replaced and ready for use. -Testing: N/A
6 ESR ORS Carbon Replacement -Materials: Lifting adapter approved by Sprouse. Estimating ~$350 for materials -Pressure System: N/A -Drawings: Need to be developed. -Fabrication: awaiting drawings -Operations: Needs to be scheduled/planned. -Testing: Spool pieces will need to be tested.
7 ESR 15K U-tube -Materials: ordered -Pressure System: signed -Drawings: issued. -Fabrication: in fabrication -Operations: U-tube will be stabbed at earliest convenience -Testing: pressure test per DPF
8 ESR Oil collection -Materials: TBD -Pressure System: TBD -Drawings: TBD -Fabrication: TBD -Operations: May require piping removal or plant shutdown -Testing: not likely. category D piping at most.
9 CHL IA modification -Materials: ordered -Pressure System: TBD -Drawings: in development -Fabrication: TBD -Operations: N/A -Testing: Initial service leak test
ESR Status
- Halls A, B, and C are on cold return. Hall C magnets filling.
- Hall C is cooling SHMS Dipole to 100K. U-tubes were stabbed Tuesday.
- Hall C target system is being cleaned. Not connected to ESR or recovery as of now.
- CHL-ESR x-fer line will be in use occasionally over the next week.
- T2 will need to be stopped to facilitate simple trouble shooting on inlet valve/actuator.
MSU FRIB
Organize and publish pressure system documentation for pressure systems. Actions are as listed in the summary document.
- IA complete
- GV complete
- LND complete
- waiting for examination docs from embler.