Difference between revisions of "Alicia Saringer work items"

From Cryowiki
Jump to navigationJump to search
Line 5: Line 5:
 
Install the C.V. on C9
 
Install the C.V. on C9
  
LCLS II Spreader Analysis (Complete), Start White Paper (Complete), Comment Adjudication (Complete), Incorporate Comments and Develop Final Draft
+
LCLS II Spreader Analysis (Complete), Start White Paper (Complete), Comment Adjudication (Complete), Incorporate Comments and Develop Final Draft(Complete)
  
 
Relief Valve Instrumentation/Protected Zones (CTF Complete)
 
Relief Valve Instrumentation/Protected Zones (CTF Complete)

Revision as of 14:49, 15 February 2017

Dunham-Bush Check Valve Hinge Installation Verification (Complete)

Recovery Compressor Pipe Analysis (Complete)

Install the C.V. on C9

LCLS II Spreader Analysis (Complete), Start White Paper (Complete), Comment Adjudication (Complete), Incorporate Comments and Develop Final Draft(Complete)

Relief Valve Instrumentation/Protected Zones (CTF Complete)

-Schedule service of two to six relief valves during shutdown. Plan for addressing all relief valves developed, RV2081, RV2420, RV2440 Ready for this shutdown, Address the relief valves on the Bayonet Cans.

-Continue to the other plants.

Liquid Level Indicator determined to go on the coalescer. Develop a drawing and plan.

CHL Recovery Compressor Header Redesign

CTF Warm-Up/Cool Down (Complete-Review Thilan's plan)-Complete

Kinney Water Line Leak-Complete

Relief Valves to Replace at CTF (Complete)

Sight Glass Assembly Installation at Kinney Pump - ETA 2/7/2017

CTF Recovery Compressor C4 and C6 P&I

Develop CTF Document - Ongoing

CTF Spreadsheets - Ongoing - Get with Bill about full startup after power outage