==ESR Status==
 
==ESR Status==
#Halls A, B, and C are on cold return.  Hall C magnets filling. 
+
#Hall A:
#Hall C is cooling SHMS Dipole to 100K.  U-tubes were stabbed Tuesday.
+
  - Magnets cold, on cold return, controlling properly
#Hall C target system is being cleaned.  Not connected to ESR or recovery as of now.
+
  - Warm flows return to ESR
#CHL-ESR x-fer line will be in use occasionally over the next week.
+
  - Target cool down scheduled 2/16/17
#T2 will need to be stopped to facilitate simple trouble shooting on inlet valve/actuator.
+
 
 +
#Hall B:
 +
  - Torus cold, on cold return, controlling properly
 +
  - Warm flows return to ESR
 +
  - Solenoid scheduled for May delivery
 +
 
 +
#Hall C:
 +
  - All magnets cold, on cold return
 +
  - Warm flows return to CHL
 +
  - SHMS magnet pressure at 1.7 atm, anaconda replacement plans being made
 +
  - Q3 and dipole testing underway.
 +
  - Initial target cool down (~1 day) scheduled for 2/20
 +
  - KPP scheduled for March

Revision as of 09:50, 16 February 2017

JLab

2/16 Update Organize cryo pressure systems

  • CHL:
  1 Replacement/upgrade of LN2 fill station gauging:
    -Materials: On-site
    -Pressure System:  Standard Maintenance
    -Drawings: N/A
    -Fabrication:  N/A
    -Operations:  Assigned Tank 2 complete.  Tank 1 is being prioritized.
    -Testing:  Snoop upon installation.
  2 CHL Guard Vacuum
    -Materials:  installed
    -Pressure System:  Signed
    -Drawings: Complete
    -Fabrication: N/A
    -Operations: Will test run upon completion of electrical and IA installation.
    -Testing:  To be initial service leak checked upon completion of electrical work.  Pump temperatures will also need to be monitored.
  3 LN2 Dewar #1 instrumentation tubing replacement
    -Materials:  On-site
    -Pressure System:  Signed
    -Drawings: Complete
    -Fabrication: All paperwork and materials are with Scott.  He is scheduling.
    -Operations: N/A
    -Testing:  To be initial service leak checked upon completion.  


  4 LN2 PBC leaks
    -Materials:  TBD
    -Pressure System:  TBD
    -Drawings: TBD
    -Fabrication: TBD
    -Operations: All leaks have been identified and tabulated.  Ops is investigating the repair of threaded connections.
    -Testing:  Snoop


  5 CHL Recovery Purifier Sieve replacement
    -Materials:  on-site
    -Pressure System:  N/A
    -Drawings: N/A
    -Fabrication: N/A
    -Operations: P5 sieve replaced and ready for use.
    -Testing:  N/A


  6 ESR ORS Carbon Replacement
    -Materials:  Lifting adapter approved by Sprouse.  Estimating ~$350 for materials
    -Pressure System:  N/A
    -Drawings: Need to be developed.
    -Fabrication: awaiting drawings
    -Operations: Needs to be scheduled/planned.  Probably next summer
    -Testing:  Spool pieces will need to be tested.
  7 ESR 15K U-tube
    -Materials:  ordered
    -Pressure System:  signed
    -Drawings: issued.
    -Fabrication: in fabrication (expect to test by 3/3/17)
    -Operations: U-tube will be stabbed at earliest convenience (when it will not impact target schedule)
    -Testing:  pressure test per DPF
  8 ESR Oil collection
    -Materials:  TBD
    -Pressure System:  TBD
    -Drawings: TBD
    -Fabrication: TBD
    -Operations: May require piping removal or plant shutdown
    -Testing:  not likely. category D piping at most.


  9 CHL IA modification
    -Materials:  ordered
    -Pressure System:  TBD
    -Drawings: in development
    -Fabrication: TBD
    -Operations: N/A
    -Testing:  Initial service leak test
  10 CHL purifier sieve heater
    -Materials:  Awaiting design
    -Pressure System:  Awaiting design
    -Drawings:  Awaiting basic design
    -Fabrication:  Awaiting drawings
    -Operations:  TBD
    -Testing: Test per B31.3, with consideration for temperature requirements.

ESR Status

  1. Hall A:
 - Magnets cold, on cold return, controlling properly
 - Warm flows return to ESR
 - Target cool down scheduled 2/16/17
  1. Hall B:
 - Torus cold, on cold return, controlling properly
 - Warm flows return to ESR
 - Solenoid scheduled for May delivery
  1. Hall C:
 - All magnets cold, on cold return
 - Warm flows return to CHL
 - SHMS magnet pressure at 1.7 atm, anaconda replacement plans being made
 - Q3 and dipole testing underway.
 - Initial target cool down (~1 day) scheduled for 2/20
 - KPP scheduled for March