'''1. Manpower '''
 
'''1. Manpower '''
  
Ritendra is working the electrical and controls package.
+
Will has asked Mike to submit his needs as related to contract designers and to submit a new manpower plan.
  
  
 
'''2. Project '''
 
'''2. Project '''
  
The 2K FDR was 9 Mar at JLAB. Reviewers have not produced a report yet but feeling is they are not at 90% design.
 
 
Internal 2K piping is being worked with Hung yu and Damon Rath.
 
 
Smith groups review of the installation package is complete.
 
 
Mike reports the upstream can design is almost complete and they are working on the downstream can.
 
  
  
 
'''3. Recovery Compressor Progress '''
 
'''3. Recovery Compressor Progress '''
  
Heat exchanges did not show up on time. When Ski called, the vendor indicated the ship date slipped one month. ITT is running three shifts to catch up.
+
Shop expects to meet July delivery.  
  
  
Line 31: Line 24:
 
There is more potential fabrication work for a turbine and cold compressor water skid but we have not heard anything else.
 
There is more potential fabrication work for a turbine and cold compressor water skid but we have not heard anything else.
  
There may also be some work building 230 bayonets, etc.
+
There may also be some work building 230 bayonets, etc. We are going to build these bayonets.
 
 
We met with Ed Daly to help him produce an estimate for the LCLS2 in LERF cryomodule testing. Daly estimated it would be required in 3-6 months. We agreed that he could use his end-can as is.
 
  
 +
We met with Ed Daly to help him produce an estimate for the LCLS2 in LERF cryomodule testing. Daly estimated it would be required in 3-6 months. We agreed that he could use his end-can as is.
  
 +
We are starting to form the skills required for commissioning support.
  
 
== Action Items ==
 
== Action Items ==
  
 
1. Kelly needs a list of duties expected to support LCLS2 for Ritendra and Swapnil.
 
1. Kelly needs a list of duties expected to support LCLS2 for Ritendra and Swapnil.

Latest revision as of 14:34, 3 April 2017

Attendance

Creel, Dixon, Oren, Bevins, Arenius

Agenda and Notes

1. Manpower

Will has asked Mike to submit his needs as related to contract designers and to submit a new manpower plan.


2. Project


3. Recovery Compressor Progress

Shop expects to meet July delivery.


4. Additional work

There is more potential fabrication work for a turbine and cold compressor water skid but we have not heard anything else.

There may also be some work building 230 bayonets, etc. We are going to build these bayonets.

We met with Ed Daly to help him produce an estimate for the LCLS2 in LERF cryomodule testing. Daly estimated it would be required in 3-6 months. We agreed that he could use his end-can as is.

We are starting to form the skills required for commissioning support.

Action Items

1. Kelly needs a list of duties expected to support LCLS2 for Ritendra and Swapnil.