Meeting Feb 13, 2016
Attendance
Creel, Scanlon, Oren, Bevins, Arenius
Agenda and Notes
1. Manpower
Ritendra starts Thursday. He will start on LCLS2.
New LCLS2 manpower plan anticipated by Monday next week so we can adjust plan.
2. Project
The 2K FDR is scheduled 8 Mar at JLAB.
The controls design workshop was at SLAC 8 Feb. Scanlon says requirements keep changing. It was a procurement readiness review but now they are asking for ICD's FRS's etc. Post review should allow Chris to release gas management and utility ($500K) and then the 4K and 2K cold boxes ($500K) (paperwork is at 80% complete). In addition, Vincent has requested the written software spec also be translated in to flow chart form. Creel told Chris this would need to be a formal change request through Dana since it will involve additional manpower and resources that were not accounted for in the current manpower plan.
Internal 2K piping is being worked with Hung yu and Damon Rath.
Smith groups review of the installation package is complete. They came up with a number of recommendations. Dana needs help identifying locations of field mounted devices.
3. Recovery Compressor Progress
Assembling frames and piping components. The compressor bodies have arrived and were inspected.
4. Additional work
There is more potential fabrication work for a turbine and cold compressor water skid.
Creel is working with Chris to complete the software spec.
Action Items
1.
2.