02/16/2017 Meeting
Attendance
Thompson, Creel, Dixon, Michalski, Oren, Arenius
Agenda and Notes
1. Operations
MFA
No one from cryo has access to the operations screens from home. I have called Kowalski, helpdesk, and put in a CCPR.
LINAC
Normal
CHL1
CHL2
Normal
ESR
Hall C believes the high SHMS back pressure is because of the flexible anaconda. They are working on a plan.
CTF
Normal
The CTF shutdown is scheduled for tomorrow morning.
HDR
Normal. The solenoid did have an issue with their LN2 control valve. Problem was solved but no one really knows why.
2. Projects
UIM
Shutdown scheduled for Feb 17.
UITF
Thermosiphon is being fabricated.
MSU
Working to accumulate the pressure systems documentation.
LCLS2
Ritendra starts today he will be assigned to the LCLS2 Monday to help with controls. The ECAD designer was extended through May.
3. Manpower
Ritendra starts today. He has an office and has a computer.
4. Info from Will
1. LN2 contract proposals are in and have been routed to DOE for approval.
2. New director starts Apr 3.
3. Let Will know if anyone approaches us to provide an estimate for installing an LCLS2 module in LERF.
4. Funding could impact summer shutdown schedule possibly forcing the shutdown of CHL2 earlier than the May bill read. Possibly as early as 23 March. We are moving ahead with electrical installation and fabrication of the piping spools for this job.
5. LERF is still hoping to get the medical isotope contract in 18'
5. Other
Machie send out a request asking how many people still use ME10.
Action Items
1. Must keep meeting to no more than 30 minutes
2. Plan the replacement of the SC2 power feedthrus.
Action Item Updates
1. Kandice Carter took pictures of two of our new engineers for engineers week.
2.