Attendance

Creel, Dixon, Scanlon, Oren, Bevins, Arenius


Agenda and Notes

1. Manpower

Ritendra B. has started. He has been placed on LCLS2. Chris has been instructed to get Ritendra busy on the controls work as fast as possible. Will continues to get pushing from John Galita via Joe P.


2. Project

The 2K FDR is scheduled 9 Mar at JLAB.

The controls design workshop was at SLAC 8 Feb. Scanlon says requirements keep changing. It was a procurement readiness review but now they are asking for ICD's FRS's etc. Post review should allow Chris to release gas management and utility ($500K) and then the 4K and 2K cold boxes ($500K) (paperwork is at 80% complete). In addition, Vincent has requested the written software spec also be translated in to flow chart form. Creel told Chris this would need to be a formal change request through Dana since it will involve additional manpower and resources that were not accounted for in the current manpower plan.

Internal 2K piping is being worked with Hung yu and Damon Rath.

Smith groups review of the installation package is complete.

Mike reports the upstream can design is almost complete and they are working on the downstream can.


3. Recovery Compressor Progress

Heat exchanges did not show up on time. When Ski called, the vendor indicated the ship date slipped one month. ITT is running three shifts to catch up.


4. Additional work

There is more potential fabrication work for a turbine and cold compressor water skid but we have not heard anything else.

There may also be some work building bayonets, etc.


Action Items

1. Ritendra needs to come up to speed quickly.

2. It appears shop has been charging to the cold box code instead of the recovery compressor code.

3. Add Kelly to Annie's group charge email